Question

An investment provides annual cash flows of $1200 for 9 years at a cost today of...

An investment provides annual cash flows of $1200 for 9 years at a cost today of $5200. If the company’s hurdle rate is 8% should they accept the project and why? And what if the hurdle rate is 24%? Calculate the project’s IRR

Homework Answers

Answer #1

Let cash flows for year t be CFt

Given, CF0 = -5200
CF1 to CF9 = 1200

Hurdle Rate = r

NPV = ΣCFt/(1+r)t

= -5200 + 1200/(1+r) + 1200/(1+r)2 + ..... + 1200/(1+r)9

= -5200 + 1200[1- (1+r)-9]/r

When r = 8%, NPV = -5200 + 1200[1- (1+0.08)-9]/0.08 = $2296.27 => Accept the project since NPV > 0

When r = 24%, NPV = -5200 + 1200[1- (1+0.24)-9]/0.24 = $-921.40 => Reject the project since NPV < 0

Let IRR = i

IRR is the rare at which NPV = 0

=> -5200 + 1200[1- (1+i)-9]/i = 0

=> 1200[1- (1+i)-9]/i = 5200

Using hit and trial, i = 0.2065 or 20.65%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project that provides annual cash flows of $11,300 for 9 years costs $60,209 today. a....
A project that provides annual cash flows of $11,300 for 9 years costs $60,209 today. a. If the required return is 16 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $2,900 for 10 years costs $15,300 today. Required:...
A project that provides annual cash flows of $2,900 for 10 years costs $15,300 today. Required: (a) If the required return is 8 percent, what is the NPV for this project? (b) Determine the IRR for this project.
A project that provides annual cash flows of $12,500 for 8 years costs $65,000 today. At...
A project that provides annual cash flows of $12,500 for 8 years costs $65,000 today. At what discount rate would you be indifferent between accepting the project or rejecting it? If the required rate of return is 9%, what is the profitability index of this project?   
A project that provides annual cash flows of $20,500 for 7 years costs $82,000 today. a....
A project that provides annual cash flows of $20,500 for 7 years costs $82,000 today. a. If the required return is 10 percent, what is the NPV for this project? Determine the IRR for this project.
A project that provides annual cash flows of $12,800 for 12 years costs $87,215 today.   ...
A project that provides annual cash flows of $12,800 for 12 years costs $87,215 today.    a. If the required return is 13 percent, what is the NPV for this project?    b. Determine the IRR for this project.
A project that provides annual cash flows of $12,500 for 8 years costs $65,000 today. At...
A project that provides annual cash flows of $12,500 for 8 years costs $65,000 today. At what discount rate would you be indifferent between accepting the project or rejecting it? If the required rate of return is 9%, what is the profitability index of this project?    Please show work and calculation don't do it on excel
34. A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today....
34. A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a. If the required return is 10 percent, what is the NPV for this project? a. If the required return is 10 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $11,700 for nine years costs $63,000 today. What...
A project that provides annual cash flows of $11,700 for nine years costs $63,000 today. What is the NPV for the project if the required return is 8 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) At a required return of 8 percent, should the firm accept this project? Accept Reject What is the NPV for the project if the required return is 20 percent? (A negative answer should be indicated by...
A project that provides annual cash flows of $17,300 for nine years costs $79,000 today. THREE...
A project that provides annual cash flows of $17,300 for nine years costs $79,000 today. THREE QUESTIONS: What is the NPV for the project if the required return is 8 percent What is the NPV for the project if the required return is 20 percent At what discount rate would you be indifferent between accepting the project and rejecting it ?
Calculating NPV and IRR. A project that provides annual cash flows of $1,710 for 10 years...
Calculating NPV and IRR. A project that provides annual cash flows of $1,710 for 10 years costs $7,560 today. 1. The NPV is $__________if the required rate of return is 10%. 2. The NPV is $__________if the required rate of return is 24%. 3. At what discount rate would you be indifferent between accepting the project and rejecting it? I would be indifferent at _____% 4. Using a finnancial calculator please show and explain work.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT