Question

Assuming a project having the following cash flows: Year 0 1 2 3 4 Cash flow...

Assuming a project having the following cash flows:

Year

0

1

2

3

4

Cash flow

-6000

500

-500

5000

3000

  1. What is the NPV of this project if the discount rate is 5%?

Report the answer with 2 numbers after decimal place

  1. What is the IRR of this project?

Report the answer in percentage term with 2 numbers after decimal place such as 12.43%.

  1. What discount rate will make NPV of this project equals to -494.258

Report the answer in percentage term with 2 numbers after decimal place

PLEASE SHOW WORK USING EXCEL

Homework Answers

Answer #1

Using excel formula to calculate NPV and IRR

A B C D E
Year 0 1 2 3 4
1 Cash flow -6000 500 -500 5000 3000
NPV 809.97 Using Excel formula=NPV(5%,B1:E1)+A1
IRR 9.13% Using Excel formula=IRR(A1:E1)

c. Discount Rate using excel formula

A B C D E
Year 0 1 2 3 4
1 Cash flow -6000 500 -500 5000 3000
2 NPV -494.258
3 Cash flow Difference -5505.742 500 -500 5000 3000
Discount Rate 12.05% Using Excel formula=IRR(A3:E3)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Answer Question 1-3 Project A has the following projected cash flows: Year           Cash Flow 0                -11,23
Answer Question 1-3 Project A has the following projected cash flows: Year           Cash Flow 0                -11,235 1                4,400 2                4,400 3                4,400 4                4,400 5                7,400 Q1) The NPV of the above project is $_____. Assume a discount rate of 6%. a)9541 b)20776 c)17623 d)6388 Q2) The IRR for the above project is __ %. a)21.09 b)26.76 c)33.95 d)31.25 Q3)Which of the following statement is correct? a)If the discount rate increases, the IRR will decrease. b)If the discount rate increases, the NPV will stay the same. c)If...
A project has the following cash flows: Year Cash Flow 0 –$ 15,400 1 6,100 2...
A project has the following cash flows: Year Cash Flow 0 –$ 15,400 1 6,100 2 7,400 3 5,900 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ 4,000 What is the NPV at a discount rate of 8 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ 1,276.06 What is...
A project has the following cash flows: Year Cash Flow 0 –$ 16,600 1 7,300 2...
A project has the following cash flows: Year Cash Flow 0 –$ 16,600 1 7,300 2 8,600 3 7,100 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) What is the NPV at a discount rate of 12 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) What is the NPV at a discount rate...
QUESTION 1 Year Cash flow 0 -1075 1 350 2 450 3 375 4 300 A...
QUESTION 1 Year Cash flow 0 -1075 1 350 2 450 3 375 4 300 A firm is evaluating a potential capital expenditure project. The project will last for 4 years and has the above expected cash flows. The firm has a WACC of 15%. What is the project's NPV? If NPV is negative, enter the number with a minus sign. Use 2 decimal places Year Cash flow 0 -1075 1 350 2 450 3 375 4 300 The firm...
A project has the following cash flows: Year Cash Flow 0 $ 72,500 1 –51,500 2...
A project has the following cash flows: Year Cash Flow 0 $ 72,500 1 –51,500 2 –28,000 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 6 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your...
What is the IRR for a project with the following cash flows: Year 0 −5000, Year...
What is the IRR for a project with the following cash flows: Year 0 −5000, Year 1 +3000, Year 2 +4000? A)10.1%B)15.0%C)24.3% D)31.0%
Consider the following cash flows: Year Cash Flow 0 –$ 34,000   1 15,100   2 16,600   3...
Consider the following cash flows: Year Cash Flow 0 –$ 34,000   1 15,100   2 16,600   3 12,500   a. What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) b. What is the NPV at a discount rate of 8 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) c. What is the NPV at a discount...
Telesis Corp is considering a project that has the following cash flows: Year Cash Flow 0...
Telesis Corp is considering a project that has the following cash flows: Year Cash Flow 0 -$1,000 1 400 2 300 3 500 4 400 The company’s weighted average cost of capital (WACC) is 10%. What are the project’s payback period (Payback), internal rate of return (IRR), net present value (NPV), and profitability index (PI)? A. Payback = 3.5, IRR = 10.22%, NPV = $1260, PI=1.26 B. Payback = 2.6, IRR = 21.22%, NPV = $349, PI=1.35 C. Payback =...
A project costs $5,000 at t = 0 and will generate annual cash flows of $750...
A project costs $5,000 at t = 0 and will generate annual cash flows of $750 for 10 years, starting at t = 1. The discount rate is 6%. What is the NPV? What is the IRR? (Write down the equation for the IRR and get the solution using Excel or the calculator.) A project costs $5,000 and will generate annual cash flows of $200 in the first year, $300 in the second year and $400 in the third year....
A project has the following projected cash flows Year 0- R280,000( investment) Year 1 R70,000 Year...
A project has the following projected cash flows Year 0- R280,000( investment) Year 1 R70,000 Year 2 R100,000 Year 3 R130,000 a) Assuming a discount rate of 10% what is the Net Present Value (NPV) of this project over the 3 year period? b) Based on your answer above, should the project be recommended for acceptance? c) would your answer to b above change if the discount rate was 5%? Why? d) what do you understand by the term nominal...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT