QUESTION 10 The discount rate is 5% per annum, and there is project that requires an initial investment of $25 million. If this project earns $5 million in Yr 1, $12 million in Yr 2 and $7 million in Yr 3, what is the net present value of the project?
- 5.47 million dollars
- 2.14 million dollars
+ 3.31 million dollars
- 3.31 million dollars
NPV :
NPV is the difference between Present value of Cash Inflows and
Present value of cash outflows.
NPV = PV of Cash Inflows - PV of Cash Outflows
If NPV > 0 , Project can be accepted
NPV = 0 , Indifference point. Project can be accepted/
Rejected.
NPV < 0 , Project will be rejected.
Year | CF | PVF @5 % | Disc CF |
0 | $ -25,000,000.00 | 1.0000 | $ -25,000,000.00 |
1 | $ 5,000,000.00 | 0.9524 | $ 4,761,904.76 |
2 | $ 12,000,000.00 | 0.9070 | $ 10,884,353.74 |
3 | $ 7,000,000.00 | 0.8638 | $ 6,046,863.19 |
NPV | $ -3,306,878.31 |
NPV is -3.31 Million
OPtion D is correct.
Get Answers For Free
Most questions answered within 1 hours.