Question

Question 1. What is the INTERNAL RATE OF RETURN for project A? (Assume a discount rate...

Question 1.

What is the INTERNAL RATE OF RETURN for project A? (Assume a discount rate of 8%)

Year Project A Project Z
0 -$35,000 -$350,000
1 17,000 110,000
2 17,000 110,000
3 16,000 105,000
4 15,000 100,000
5 14,000 100,000

36.74%

32.24%

28.71%

22.65%

Question 2.

What is the PROFITABILITY INDEX for project A? (Assume a discount rate of 8%)

Year Project A Project Z
0 -$35,000 -$350,000
1 17,000 110,000
2 17,000 110,000
3 16,000 105,000
4 15,000 100,000
5 14,000 100,000

0.20

0.41

0.82

0.95

Homework Answers

Answer #1

1.Let irr be x%
At irr,present value of inflows=present value of outflows.

35000=17000/1.0x+17000/1.0x^2+16000/1.0x^3+15000/1.0x^4+14000/1.0x^5

Hence x=irr=36.74%(Approx).

2.Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=17000/1.08+17000/1.08^2+16000/1.08^3+15000/1.08^4+14000/1.08^5

=$63570.43

NPV=Present value of inflows-Present value of outflows

=$63570.43-$35000

=$28570.43

PI=NPV/Present value of outflows

=$28570.43/$35000

=0.82(Approx).

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project will generate the following cash flows. If the required rate of return is 15%,...
A project will generate the following cash flows. If the required rate of return is 15%, what is the project’s net present value? Year Cash flow 0 –$50,000 1 $15,000 2 $16,000 3 $17,000 4 $18,000 5 $19,000 Select one: a. $16,790.47 b. $6,057.47 c. $3,460.47 d. $1,487.21 e. –$3,072.47 Question 5 Not yet answered Marked out of 1.00 Flag question Question text A project will generate the following cash flows. The required rate of return is 15%. If the...
. Calculate the IRR and NPV for the following cash flows. Assume a 15% discount rate...
. Calculate the IRR and NPV for the following cash flows. Assume a 15% discount rate Year Project 1 Cash flow Project 2 Cash flow 0 -$20,000 -$20,000 1 1,000 12,000 2 3,000 15,000 3 4,000 3,000 4 12,000 4,000 5 15,000 1,000 9. If your tenant pays you rent of $24,000 a year for 10 years, what is the present value of the series of payments discounted at 10% annually? 10. You are going to invest $300,000 in a...
Internal rate of return For the project shown in the following​ table, calculate the internal rate...
Internal rate of return For the project shown in the following​ table, calculate the internal rate of return ​(IRR). Then​ indicate, for the​ project, the maximum cost of capital that the firm could have and still find the IRR acceptable. The​ project's IRR is ​%. (Round to two decimal​ places.) Initial investment ​(CF 0CF0​) $110,000 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 $25,000 2 $50,000 3 $30,000 4 $35,000 5 $10,000
(Question 8) Monroe, Inc., is evaluating a project. The company uses a 13.8 percent discount rate...
(Question 8) Monroe, Inc., is evaluating a project. The company uses a 13.8 percent discount rate for this project. Cost and cash flows are shown in the table. What is the NPV of the project Year 0 1 2 3 4 5 project $11,368,00 $2,157,590 $3,787,552, $3,275,650 $4,115,899 $4,556,424 Round to two decimal places. (Question 8) Monroe, Inc., is evaluating a project. The company uses a 13.8 percent discount rate for this project. Cost and cash flows are shown in...
Find the modified internal rate of return for the following annual series of cash flows: given...
Find the modified internal rate of return for the following annual series of cash flows: given a discounted rate of 10.50%: year 0 - 60,000$: year 1: 15,000$, Year 2: 16,000$, Year 3:17,000$ and year 4: 17,00$
Consider the following two mutually exclusive projects: Year Project A Project B 0 -180,000 -18,000 1...
Consider the following two mutually exclusive projects: Year Project A Project B 0 -180,000 -18,000 1 60,000 15,000 2 100,000 15,000 3 150,000 12,000 Calculate the internal rate of return, and net present value. Assume a discount rate of 15%. Which project should be selected?
Net Present Value Problem Discount rate 12% Project 1 Year 1 Year 2 Year 3 Year...
Net Present Value Problem Discount rate 12% Project 1 Year 1 Year 2 Year 3 Year 4 Year 5 TOTAL Costs 220,000 35,000 35,000 25,000 20,000 ? Discount factor ? ? ? ? ? Discounted costs ? ? ? ? ? ? Benefits 0 80,000 80,000 65,000 60,000 ? Discount factor ? ? ? ? ? ? Discount benefits ? ? ? ? ? ? Discounted benefits – Discounted costs (NPV) ? ? ? ? ? ? ROI = ???...
Calculate the internal rate of return on the following project. The project will not change the...
Calculate the internal rate of return on the following project. The project will not change the firm’s market risk. If the firm’s cost of capital is 12%, should management ace pt the project? (15 pts) Year Cash Flows 0 P    751,150 1 400,000 2 300,000 3 200,000 4 100,000 With solution pls thank you!
The two projects are as follows. Discount rate = 10%.                   Project X     Project...
The two projects are as follows. Discount rate = 10%.                   Project X     Project Y                   Year     Cash-Flow     Cash-Flow                          0       -$100,000     -$100,000                          1          50,000        10,000                          2          40,000        30,000 3 30,000        40,000                         4.         10,000        60,000 Calculate the payback period of project X 1.33 years 2.33 years 3.33 years 4.33 years Calculate the crossover rate. 6.93% 6.58% 10.00% 7.17% Imagine that discount is 5%, and the two projects are mutually exclusive, which project shall you choose?...
Question 2: What is the internal rates of return (IRR) for the project that has an...
Question 2: What is the internal rates of return (IRR) for the project that has an initial outlay of $10,000 and a single cash inflow of $17,182 in 8 years? Question 3: Assume that a new project will annually generate revenues of $2,000,000 and cash expenses (including both fixed and variable costs) of $800,000, while increasing deprecation by $200,000 per year. In additional, the firm’s tax rate is 34%. Calculate the operating cash flows for the new project
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT