Question

Wildhorse Industries management is planning to replace some existing machinery in its plant. The cost of...

Wildhorse Industries management is planning to replace some existing machinery in its plant. The cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses an 18 percent discount rate for projects like this. Should management go ahead with the project?

Year Cash Flow

0

-$3,485,400

1

871,710

2

896,700

3

1,104,400

4

1,340,360

5

1,450,600


What is the NPV of this project? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to 0 decimal places, e.g. 1,525.)

The NPV is ?

$enter The NPV in dollars rounded to 0 decimal places

"what is the NPV?"


Should management go ahead with the project?

The firm should select an option                                                          reject accept the project.

Homework Answers

Answer #1
  1. Calculation of NPV (Net Present Value)

Answer: NPV =$6,865,719

NPV = Present Value of future cash inflows – Initial Investment

Calculation of Present value of cash inflows for project

Year

Cash Flow

Present Value Factor @ 18% (Required rate of return)

Present Value of cash flow

(I)

(II)

(III)

(II) * (III)

1

$   871,710

0.847458

$      738,737.61

2

$   896,700

0.718184

$      643,995.59

3

$1,104,400

0.608631

$      672,172.08

4

$1,340,360

0.515789

$      691,342.94

5

$1,450,600

0.437109

$      634,070.32

Present Value of the Cash flows inflows

$ 3,380,318.54

Initial Investment =$3,485,400/- (provided in the question)

NPV = Present Value of future cash inflows – Initial Investment

NPV = $3,380,318.54 – $3,485,400.

                   =$6,865,718.54

                   =$6,865,719

Calculation of Discounting Factor (Present Value Factor)

Discount Factor = 1/ (1+R) N

R = Discount Rate (i.e. = 18%)

N = No of years

E.g. for year 2 Discount Factor = 1/ (1.18)2

                                                                = 1/ (1.18) (1.18)

                                                =0.718184

  1. What is NPV

  1. Should management go ahead with the project?

Accept the project, since NPV is positive (i.e. NPV of$6,865,719)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Crescent Industries management is planning to replace some existing machinery in its plant. The cost of...
Crescent Industries management is planning to replace some existing machinery in its plant. The cost of the new equipment and the resulting cash flows are shown in the accompanying table. If the firm uses an 18 percent discount rate for projects like this. Year Cash Flow 0 -$3,379,600 1 $788,310 2 $898,600 3 $1,137,500 4 $1,212,360 5 $1,602,800 What is the NPV of this project? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round other...
Crescent Industries management is planning to replace some existing machinery in its plant. The cost of...
Crescent Industries management is planning to replace some existing machinery in its plant. The cost of the new equipment and the resulting cash flows are shown in the accompanying table. If the firm uses an 18 percent discount rate for project. Year Cash Flow 0 -$3,524,500 1 $938,910 2 $969,800 3 $1,149,000 4 $1,263,360 5 $1,409,200 What is the NPV of this project? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round intermediate calculations to...
Net present value: Crescent Industries is planning to replace some existing machinery in its plant. The...
Net present value: Crescent Industries is planning to replace some existing machinery in its plant. The cost of the new equipment and the resulting cash flows are shown in the accompanying table. Year Cash Flow 0 -$3,493,710 1 $816,490 2 $930,375 3 $1,216,906 4 $1,341,053 5 $1,392,665 If the company uses an 18 percent discount rate for project like this, the NPV is $____, and the company should reject or accept the project?
Please answer both parts of this question. Carla Vista Corp. management is planning to spend $650,000...
Please answer both parts of this question. Carla Vista Corp. management is planning to spend $650,000 on a new marketing campaign. They believe that this action will result in additional cash flows of $313,000 each year for three years. If the discount rate is 17.5 percent, what is the NPV on this project? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to 0 decimal places, e.g. 1,525.) Oriole,...
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,292,224 -$1,321,796 1 238,000 384,000 2 329,000 384,000 3 430,000 384,000 4 504,000 384,000 5 800,000 384,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to...
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,304,168 -$1,325,262 1 264,000 379,000 2 365,000 379,000 3 445,000 379,000 4 539,000 379,000 5 739,000 379,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to...
Cullumber Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive,...
Cullumber Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 9 percent discount rate for their production systems. Year System 1 System 2 0 -$15,100 -$42,300 1 15,100 30,800 2 15,100 30,800 3 15,100 30,800 What are the payback periods for production systems 1 and 2? (Round answers to 2 decimal places,...
Emporia Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given...
Emporia Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given in the following table. The firm uses 12.27 percent to discount such project cash flows. Year System 100 System 200 0 $-2,053,200 $-1,741,800 1 314,410 701,900 2 520,830 460,300 3 529,940 614,300 4 656,200 314,000 What is the NPV of the systems? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round answers to 0 decimal places, e.g. 5,275.) NPV...
Blossom Corp. management is planning to convert an existing warehouse into a new plant that will...
Blossom Corp. management is planning to convert an existing warehouse into a new plant that will increase its production capacity by 45 percent. The cost of this project will be $8,467,824. It will result in additional cash flows of $2,312,200 for the next eight years. The discount rate is 11.83 percent. Excel Template (Note: This template includes the problem statement as it appears in your textbook. The problem assigned to you here may have different values. When using this template,...
Blossom Corp. management is investigating two computer systems. The Alpha 8300 costs $3,324,225 and will generate...
Blossom Corp. management is investigating two computer systems. The Alpha 8300 costs $3,324,225 and will generate cost savings of $1,213,225 in each of the next five years. The Beta 2100 system costs $4,000,500 and will produce cost savings of $1,115,750 in the first three years and then $2 million for the next two years. The company’s discount rate for similar projects is 14 percent. What is the NPV of each system? (Enter negative amounts using negative sign, e.g. -45.25. Do...