Q.1 Make a Gantt chart for the information below. (Different highlighted colours for each criteria)
task name | date start | days to complete | |
criteria 1 | Aug-21 | 27 | |
criteria 2 | Aug-29 | 19 | |
criteria 3 | Sep-12 | 16 | |
criteria 4 | Sep-23 | 23 | |
criteria 5 | Sep-25 | 14 | |
criteria 6 | Sep-19 | 21 | |
criteria 7 | Aug-18 | 56 | |
criteria 8 | Aug-23 | 23 | |
Although the question is from Operation, I am giving the solution below which is prepared in the excel sheet.
The Solution is attached herewith:
Hope it will serve the purpose.