Question

The following are the net cash flows for a project under consideration: F0 = - $100,000...

The following are the net cash flows for a project under consideration:

F0 = - $100,000

F1 = - $2,000

F2 = - $77,200

F3 = - $3,920

F4 = $232,848

     a) Find all valid rates of return for this project

     b) For what range of MARR should this project be accepted using FW as the figure of merit?

Homework Answers

Answer #1

Valid rate of return is Internal rate of return (IRR)

And IRR is rate of return at which Net Present value (NPV) is zero,

And NPV is zero when Present value of inflow = Present value of Outflow

:- $232848*PVF(r%,4period) = $100000 + $2000*PVF(r%,1period) + $77200*PVF(r%,1period) + $3920*PVF(r%,1period)

To calculate IRR(r) use hit and traial approach

Let r be 10%, then NPV = -9493.94

If r = 8%, then NPV will be = 0

Thus IRR = 8%

b) If IRR> MARR i.e when MAAR is less than 8% then this project should be accepted.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Problem Two You are considering two mutually exclusive projects with the following cash flows: Project C/F0...
Problem Two You are considering two mutually exclusive projects with the following cash flows: Project C/F0 C/F1 C/F2 C/F3 C/F4 C/F5 C/F6 A $(41,215) $12,500 $14,000 $16,500 $18,000 $20,000 N/A B $(46,775) $15,000 $15,000 $15,000 $15,000 $15,000 $15,000 A) Assuming that the discount rate for project A is 16% and the discount rate for B is 15%, then given that these are mutually exclusive projects, which project would you take and why? B) If you are one of the management...
Marielle Machinery Works forecasts the following cash flows on a project under consideration. It uses the...
Marielle Machinery Works forecasts the following cash flows on a project under consideration. It uses the internal rate of return rule to accept or reject projects. C0 C1 C2 C3 − $ 10,200 0 + $ 7,700 + $ 8,700 Calculate the IRR. (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places.) IRR % ? Should this project be accepted if the required return is 14%? Yes No
7. The (net) cash flows of project X are shown below: Year (Net) Cash Flows ($)...
7. The (net) cash flows of project X are shown below: Year (Net) Cash Flows ($) 0 -10,000 1 35,200 2 -29,751 a. What are the multiple internal rates of return of project X? (1 point) b. Draw the approximate NPV profile of project X. (1 point) c. Should this project be accepted if the cost of capital is 10%? Why? (0.5 point)
Problem Two You are considering two mutually exclusive projects with the following cash flows: (Please show...
Problem Two You are considering two mutually exclusive projects with the following cash flows: (Please show calculations) Project C/F0 C/F1 C/F2 C/F3 C/F4 C/F5 C/F6 A $(41,215) $12,500 $14,000 $16,500 $18,000 $20,000 N/A B $(46,775) $15,000 $15,000 $15,000 $15,000 $15,000 $15,000 A)Assuming that the discount rate for project A is 16% and the discount rate for B is 15%, then given that these are mutually exclusive projects, which project would you take and why? B) If you are one of...
Here are the cash flows for a project under consideration: C0 C1 C2 −$8,010 +$5,940 +$20,160...
Here are the cash flows for a project under consideration: C0 C1 C2 −$8,010 +$5,940 +$20,160 a. Calculate the project’s net present value for discount rates of 0, 50%, and 100%. (Round your answers to the nearest whole dollar.) b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a whole percent.)
Here are the cash flows for a project under consideration: C0 C1 C2 −$7,020 +$4,860 +$18,360...
Here are the cash flows for a project under consideration: C0 C1 C2 −$7,020 +$4,860 +$18,360 a. Calculate the project’s net present value for discount rates of 0, 50%, and 100%. (Round your answers to the nearest whole dollar.) b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a whole percent.)
A project has the following total (or net) cash flows.                ________________________________________             
A project has the following total (or net) cash flows.                ________________________________________                 Year         Total (or net) cash flow                ________________________________________ 1 $50,000 2 70,000 3 80,000 4 100,000 _______________________________________    The required rate of return on the project is 13 percent. The initial investment (or initial cost or initial outlay) of the project is $100,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project.
A project has the following total (or net) cash flows.                ________________________________________             
A project has the following total (or net) cash flows.                ________________________________________                 Year         Total (or net) cash flow                ________________________________________ 1 $50,000 2 70,000 3 80,000 4 100,000 _______________________________________    The required rate of return on the project is 13 percent. The initial investment (or initial cost or initial outlay) of the project is $100,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project.
You are considering a project with the following set of cash flows: Cash flow 0 -5,500...
You are considering a project with the following set of cash flows: Cash flow 0 -5,500 1 2,000 2 3,000 3 1,000 4 2,000 a. What is the payback period of this project? If the pre-specified cut off is 3 years, should this project be accepted? b. What is the discounted payback period of this project? If the pre-specified cut off is 3 years, should this project be accepted? The discount rate is 10%.
The project has projected cash flows as follows. The cost of capital (k) is 10% and...
The project has projected cash flows as follows. The cost of capital (k) is 10% and the payback period is 2.8 years. Should the project be accepted under the mirr decision method? Year. Cash flow 0. -100,000 1. 40,000 2. ?? 3. 50,000
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT