Question

Suppose you are managing a project that is expected to be completed in 8 months at...

Suppose you are managing a project that is expected to be completed in 8 months at a cost of R10 000 per month. After 2 months, you realize that the project is 30% completed at a cost of R40 000. What is your analysis on the performance of the project after 2 months?

Homework Answers

Answer #1

*any doubt please comment

Total budgeted cost of the project = 8* 10,000 = 80,000

The proportionate budgeted cost for 30% completion = 80,000 * 30% = 24,000

Variance = 40,000 - 24,000 = 16000 unfavorable

The costs have overshot by 16,000 for two months when the ideal costs for 2 months must be around R 24,000. There is a variance of around 167% [40,000/ 24,000] which must be investigated by the company for incurring expenses than budgeted. This can be due to increase in variable costs or mismanagement of funds as well.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are evaluating a project that will cost $ 456 comma 000​, but is expected to...
You are evaluating a project that will cost $ 456 comma 000​, but is expected to produce cash flows of $ 124 comma 000 per year for 10 ​years, with the first cash flow in one year. Your cost of capital is 11.2 % and your​ company's preferred payback period is three years or less. a. What is the payback period of this​ project?
You are evaluating a project that will cost $ 515, 000 ​, but is expected to...
You are evaluating a project that will cost $ 515, 000 ​, but is expected to produce cash flows of $ 122 comma 000 per year for 10 ​years, with the first cash flow in one year. Your cost of capital is 11.1 % and your​ company's preferred payback period is three years or less. a. What is the payback period of this​ project? b. Should you take the project if you want to increase the value of the​ company?...
Assume you have completed a capital budgeting analysis of building a new plant on land you...
Assume you have completed a capital budgeting analysis of building a new plant on land you own, and the project's NPV is $100 million. You now realize that instead of building the plant, you could build a parking garage, and would generate a pre tax revenue of $22 million. The project would last 3 years, the corporate tax rate is 40%, and the WACC is 9%. What is the new NPV of the project, after incorporating the effect of the...
A company is considering the purchase of a 30-tonne hoist. The first cost is expected to...
A company is considering the purchase of a 30-tonne hoist. The first cost is expected to be $230 000. Net savings will be $35 000 per year over a 12-year life, and it will be salvaged for $30 000. If the company's after-tax MARR is 8 percent and it is taxed at 45 percent, what is the present worth of this project? The depreciation rate is 20%.
8. A project requires a $219,000 investment in equipment. The equipment is expected to worth $128,000...
8. A project requires a $219,000 investment in equipment. The equipment is expected to worth $128,000 when the project ends in 7 years. Operating savings are expected to be $12,000 in the first year and are expected to increase 5% per year for the life of the project. The CCA rate is 30%, the firm's discount rate is 13%, and the company’s tax rate is 22%. What is the after-tax present value of the annual operating savings? (Do not round...
You are a Project Manager of a project to build a ten-story building. At the beginning...
You are a Project Manager of a project to build a ten-story building. At the beginning of the project you were targeted to build one floor per month. The planned cost per floor is €500,000. It is now month 8 and you have completed 9 floors and the total costs to date are €4,750,000. Calculate the following: CV; SV; CPI; EAC;
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent...
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent Completed A 3.00 - 15000 1.00 B 1.00 A 5000 0.00 C 2.00 A 10000 1.00 D 3.00 A 21000 0.50 E 2.00 B,C 32000 0.00 F 1.00 C 5000 0.00 G 1.00 C 5500 0.00 The project started on June 1st. The project has a planned duration of 7 months. Data below are planned cost and actual cost (spent) from June to November:...
You are considering investing in a project in Mexico. The project will be a 2 year...
You are considering investing in a project in Mexico. The project will be a 2 year project, has an initial cost of 100K USD, and expected after tax profit of 1 million MXP per year. You expect the MXP to be valued at 0.12 USD/MXP. There are two major risks that you think have the potential to significantly affect project performance, which you assume are independent: * You think with probability of 0.19 that the MXP will depreciate to 0.1...
Assume that you are managing a risky portfolio with expected rate of return of 18% and...
Assume that you are managing a risky portfolio with expected rate of return of 18% and standard deviation of 28%. The T-bill rate is 8%. Your client chooses to invest 70% of a portfolio in your fund and 30% in a T-bill money market fund. Also, the client’s expected return of the portfolio is 15% and the standard deviation of the rate of return on his portfolio is 19.6%. Suppose that your risky portfolio includes the following investments in the...
Suppose that you have just completed the mechanical design of a​ high-speed automated palletizer that has...
Suppose that you have just completed the mechanical design of a​ high-speed automated palletizer that has an investment cost of ​$2,600,000. The existing palletizer is quite old and has no salvage value. The market value for the new palletizer is estimated to be ​$160,000 after five years. One million pallets will be handled by the palletizer each year during the five​-year expected project life. What net savings per pallet​ (i.e., total savings less​ expenses) will have to be generated by...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT