Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 9%.
0 | 1 | 2 | 3 | 4 | ||||||
Project A | -1,300 | 640 | 310 | 280 | 400 | |||||
Project B | -1,300 | 240 | 245 | 430 | 850 |
What is Project A’s IRR? Do not round intermediate calculations. Round your answer to two decimal places.
%
What is Project B's IRR? Do not round intermediate calculations. Round your answer to two decimal places.
%
If the projects were independent, which project(s) would be accepted according to the IRR method?
-Select-NeitherProject AProject BBoth projects A and BCorrect 1 of Item 3
If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method?
-Select-Neither Project AProject BBoth projects A and BCorrect 2 of Item 3
Could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive?
-Select-YesNoCorrect 3 of Item 3
The reason is -Select-the NPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same project acceptance when mutually exclusive projects are considered.the NPV and IRR approaches use different reinvestment rate assumptions and so there can be a conflict in project acceptance when mutually exclusive projects are considered.Correct 4 of Item 3
Reinvestment at the -Select-IRR WACC Correct 5 of Item 3 is the superior assumption, so when mutually exclusive projects are evaluated the -Select-NPV IRR Correct 6 of Item 3 approach should be used for the capital budgeting decision.
Using financial calculator to calculate IRR of Project A
CF0=-1300;CF1=640;CF2=310;CF3=280;CF4=400;CPT IRR =10.86%
Using financial calculator to calculate IRR of Project B
CF0=-1300;CF1=240;CF2=245;CF3=430;CF4=850;CPT IRR =10.69%
If independent project Both A and B should be selected
If mutually exclusive project then Project B should be
selected.
Yes, there could be a conflict.
The reason the NPV and IRR approaches use different reinvestment
rate assumptions so there can be a conflict in project acceptance
when mutually exclusive projects are considered.
Reinvestment at WACC is better , hence
NPV is better