While conducting Risk Analysis, a firm investigates how changes in the level of one variable will affect the overall value of a project. The firm repeats the process for other variables that they are concerned would affect value. What type of Risk Analysis is the firm doing?
Differential Sensitivity testes are done by changing the level of one variable and and observing the impact on the other class of the variables . When a sensitivity test is being undertaken , the impact of change in one of the variable is studied , while keeping the other variables constant .
The types of variables when conducting the sensitivity tests are :
No |
Type |
Description |
1 |
Test Variable |
The variable on which experimental changes are made |
2 |
Target Variable |
The variable on which expected target changes in results are obtained |
3 |
Control Variables |
Control variables for moderating the experiment |
4 |
Observational variables |
Final list of variables on which the changes are observed |
Example – Like impact in changes in sales on the 3 situations Optimistic , As expected and , Pessimistic can be done by sensitivity analysis .
Thanks