The statement is "False".
_____
Explanation:
As per the applicable rules, a prime contractor is required to submit applications for subcontractor's partial payments if the contract authorizes partials payments on termination (prior to settlement). The form that is required to be filed by the prime contractor is specified in Section 8.802-10 [Application for Partial Payment]. The prime contractor is required to attach his/her invoice to such applications for partial payments. Additionally, the prime contractor can also include his/her recommendation to such applications of subcontractors. Therefore, partial payments to terminated subcontractors under a terminated prime contract cannot be made through other than the prime contractor and the statement is false.