Question

You are offered the chance to participate in a project that produces the following cash flows:...

You are offered the chance to participate in a project that produces the following cash flows:
C0 C1 C2
+ $ 6,500 + $ 4,750 $ 14,000
The internal rate of return is 14.7%.

If the opportunity cost of capital is 14%, what is the net present value of the project? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.)

  Net present value $   
Will you accept the offer?
Yes
No

Homework Answers

Answer #1

Net present value is solved using a financial calculator. The steps to solve on the financial calculator:

  • Press the CF button.
  • CF0= $6,500.
  • Cash flow for all the years should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow, press the NPV button and enter the opportunity cost of capital of 14%.
  • Press the down arrow and CPT buttons to get the net present value.

Net Present value of cash flows at 14% opportunity cost of capital is -$105.88

The offer should not be accepted since it generates a negative net present value.

In case of any query, kindly comment on the solution.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
2. A company is considering a project that has the following cash flows: C0 = -3,000,...
2. A company is considering a project that has the following cash flows: C0 = -3,000, C1 = +900, C2 = +500, C3 = +1,100, and C4 = +1,900, with a risk-adjusted discount rate of 8%. A) Calculate the Net Present Value (NPV), Internal Rate of Return (IRR), Modified Internal Rate of Return (MIRR), and Profitability Index (PI) of this project. B) If you were the manager of the firm, will you accept or reject the project based on the...
Marielle Machinery Works forecasts the following cash flows on a project under consideration. It uses the...
Marielle Machinery Works forecasts the following cash flows on a project under consideration. It uses the internal rate of return rule to accept or reject projects. C0 C1 C2 C3 − $ 10,200 0 + $ 7,700 + $ 8,700 Calculate the IRR. (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places.) IRR % ? Should this project be accepted if the required return is 14%? Yes No
A project has the following cash flows: Year Cash Flow 0 $ 72,500 1 –51,500 2...
A project has the following cash flows: Year Cash Flow 0 $ 72,500 1 –51,500 2 –28,000 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 6 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your...
Suppose you are offered $8,800 today but must make the following payments:    Year Cash Flows...
Suppose you are offered $8,800 today but must make the following payments:    Year Cash Flows ($) 0 $ 8,800          1 −4,800          2 −3,500          3 −2,600          4 −1,400             a. What is the IRR of this offer? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)      IRR %   b. If the appropriate discount rate is 13 percent, should you accept this offer? Reject Accept c....
Suppose you are offered $10,600 today but must make the following payments:    Year Cash Flows...
Suppose you are offered $10,600 today but must make the following payments:    Year Cash Flows ($) 0 $ 10,600          1 −4,900          2 −4,400          3 −3,400          4 −2,700             a. What is the IRR of this offer? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)      IRR %   b. If the appropriate discount rate is 14 percent, should you accept this offer? Accept Reject c....
Here are the cash flows for a project under consideration: C0 C1 C2 −$8,010 +$5,940 +$20,160...
Here are the cash flows for a project under consideration: C0 C1 C2 −$8,010 +$5,940 +$20,160 a. Calculate the project’s net present value for discount rates of 0, 50%, and 100%. (Round your answers to the nearest whole dollar.) b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a whole percent.)
Here are the cash flows for a project under consideration: C0 C1 C2 −$7,020 +$4,860 +$18,360...
Here are the cash flows for a project under consideration: C0 C1 C2 −$7,020 +$4,860 +$18,360 a. Calculate the project’s net present value for discount rates of 0, 50%, and 100%. (Round your answers to the nearest whole dollar.) b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a whole percent.)
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −6,950 4,700 18,400 a. Calculate...
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −6,950 4,700 18,400 a. Calculate the net present value of the above project for discount rates of 0, 50, and 100%. NPV @ 0% $ NPV @ 50% $ NPV @100% $ b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a percent rounded to the nearest whole number.) IRR %
Aerospace Dynamics will invest $150,000 in a project that will produce the following cash flows. The...
Aerospace Dynamics will invest $150,000 in a project that will produce the following cash flows. The cost of capital is 10 percent. (Note that the fourth year’s cash flow is negative.)    Year Cash Flow 1 $ 45,000 2 57,000 3 65,000 4 (48,000 ) 5 140,000 a. What is the net present value of the project? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places.)   ...
Aerospace Dynamics will invest $100,000 in a project that will produce the following cash flows. The...
Aerospace Dynamics will invest $100,000 in a project that will produce the following cash flows. The cost of capital is 15 percent. (Note that the fourth year’s cash flow is negative.) Use Appendix B for an approximate answer but calculate your final answer using the formula and financial calculator methods.    Year Cash Flow 1 $ 50,000 2 36,000 3 30,000 4 (27,000 ) 5 60,000 a. What is the net present value of the project? (Negative amount should be...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT