Question

Calculate the NPV of a project under consideration with the following information: project life = 5...


Calculate the NPV of a project under consideration with the following information: project life = 5 years; project cost = $1,500,000; unit sales = 25,000; unit price = $200; unit variable cost = $170; fixed costs = $250,000; tax rate = 34%; rate of return = 12%.

Please show the steps on how to do this with Texas Instruments BAII Plus calculator

Homework Answers

Answer #1
Annual Operating cashflows:
CM per unit (200-170) 30
Multiply: Units sales 25000
Contribution Margin 750000
Less: Fixedd costt 250000
Less: Depreiation (1500000/5) 300000
Earnings before tax 200000
Less: tax @ 34% 68000
After tax income 132000
Add: Depreciation 300000
Annual cashflows 432000
Multiply: Annuity PVF at 12% 3.60478
Present value of cashflows 1557265
Less; Initial investment 1500000
NPV 57265
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project under consideration costs $750,000, has a five-year life and has no salvage value. Depreciation...
A project under consideration costs $750,000, has a five-year life and has no salvage value. Depreciation is Straight-Line to zero and the Tax Rate is 34 percent. Sales are projected at 500 units per year. Price per unit is $2,500, Variable Cost per unit is $1,500, and Fixed Costs are $100,000 per year. Suppose you think that the unit sales, price, variable cost, and fixed cost projections given here are accurate to within 10 percent either way. What is the...
A project under consideration costs $200,000, has a five-year life and has no salvage value. Depreciation...
A project under consideration costs $200,000, has a five-year life and has no salvage value. Depreciation is straight-line to zero. The firm has made the following projections related to this project: Base Case Lower Bound Upper Bound Unit Sales 2,000 1,800 2,200 Price Per Unit $400 $360 $440 Variable Cost Per Unit $200 $180 $220 Fixed Costs $300,000 $270,000 $330,000 The required return is 15 percent and the tax rate is 21 percent. No additional investment in net working capital...
The YayForWinterBreak Company wants to calculate the NPV and IRR on the following project: Cost is...
The YayForWinterBreak Company wants to calculate the NPV and IRR on the following project: Cost is $22,000 today, with end-of-year cash flows of $10,000, $10,000, and $6,500, Years 1 through 3 respectively for three years. Assume the cost of capital is 8%. SHOW ALL WORK on the TI BAII Plus Calculator FOR FULL CREDIT. a) (8 pts) NPV? b) (5 pts) IRR? c) (2 pts) Do you accept or reject the project, and why?
You are considering the following project. What is the NPV of the project? Project life: 3...
You are considering the following project. What is the NPV of the project? Project life: 3 years Equipment:      Cost: $18,000      Economic life: 3 years      Salvage value: $4,000 Initial investment in net working capital: $2,000 Revenue: $13,000 in year 1, with a nominal growth rate of 5% per year Fixed cost: $3,000 in year 1 Variable cost: 30% of revenue Corporate tax rate (T): 40% WACC for the project: 10% This project does not create incidental effect.
You are considering the following project. What is the NPV of the project? Project life: 3...
You are considering the following project. What is the NPV of the project? Project life: 3 years Equipment:      Cost: $18,000      Economic life: 3 years      Salvage value: $4,000 Initial investment in net working capital: $2,000 Revenue: $13,000 in year 1, with a nominal growth rate of 5% per year Fixed cost: $3,000 in year 1 Variable cost: 30% of revenue Corporate tax rate (T): 40% WACC for the project: 10% This project does not create incidental effect. Select...
XZ Inc. is considering a three-year project. The initial investment on the fixed asset will be...
XZ Inc. is considering a three-year project. The initial investment on the fixed asset will be $900,000. Fixed asset will be depreciated using straight-line method to zero over the life of the project. The net working capital investment will be $250,000. The project is estimated to generate $500,000 in annual sales, with cost of $150,000. Assume the tax rate is 34% and required return is 8%, what is the NPV of this project?
Base Lower Upper Unit Sales 6,000 5,500 6,500 Price per unit 160 150 170 VC per...
Base Lower Upper Unit Sales 6,000 5,500 6,500 Price per unit 160 150 170 VC per unit 120 116 124 FC 100,000 90,000 110,000 The Can-Do Co. is analyzing a proposed project. The company needs to purchase equipment with the initial cost of $400,000. The project has a 5-year life and equipment is straight-line depreciated to zero. At the end of the project, equipment is worth nothing. The required return is 12%, and the tax rate is 34%. Below are...
16- Calculating Project NPV Down Under Boomerang, Inc., is considering a new three-year expansion project that...
16- Calculating Project NPV Down Under Boomerang, Inc., is considering a new three-year expansion project that requires an initial fixed asset investment of $2.7 million. The fixed asset will be depreciated straight-line to zero over its three-year tax life, after which it will be worthless. The project is estimated to generate $2,400,000 in annual sales, with costs of $960,000. The tax rate is 35 percent and the required return is 15 percent. What is the project’s NPV? (20 Points) Hint:...
We are evaluating a project that costs $683988, has a five-year life, and has no salvage...
We are evaluating a project that costs $683988, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 42400 units per year. Price per unit is $50, variable cost per unit is $22, and fixed costs are $524439 per year. The tax rate is 30%, and we require a return of 18% on this project. Suppose the projections given for price, quantity, variable costs,...
The initial cost of the project is $160,000 and it has a 5-year life, with a...
The initial cost of the project is $160,000 and it has a 5-year life, with a salvage value of zero. Depreciation is straight-line; the required return is 12% and the tax rate is 30%.                                  Base Case           Lower Bound           Upper Bound Unit Sales                  5,000                     5,500                            6,000 Price/unit                   $ 80                       $ 77                               $ 85 Var. cost/unit             $ 60                       $ 57                             $ 65 Fixed cost/year         $ 50,000             $ 46,000                            $60,000 Use the...