Question

You have been assigned the task of evaluating two mutually exclusive projects with the following projected...

You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows:If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why?

YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW
0   -105,000   -105,000
1   37,000   0
2   37,000   0
3   37,000   0
4   37,000   0
5   37,000   230,000

Homework Answers

Answer #1

A:

Present value of annuity=Annuity[1-(1+interest rate)^-time period]/rate

=$37000[1-(1.11)^-5]/0.11

=$37000*3.695897018

=$136,748.19

NPV=Present value of inflows-Present value of outflows

=$136,748.19-$105000

=$31,748.19(Approx).

B:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=230,000/1.11^5

=$136,493.81

NPV=Present value of inflows-Present value of outflows

=$136,493.81-$105000

=$31,493.81(Approx).

Hence A must be selected having higher NPV.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A cash flow Project B cash flow 0 ​$(110,000​) ​$(110,000​) 1    30,000            00 2    30,000            00 3    30,000            00 4    30,000            00 5   30,000   230,000 If the appropriate discount rate on these projects is 8​%, which would be chosen and​ why?
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(90,000​) ​$(90,000​) 1    32,000            0 2    32,000            0 3    32,000            0 4    32,000            0 5    32,000   240,000 If the appropriate discount rate on these projects is 9 ​percent, which would be chosen and​ why? The NPV of Project A is ​$ _______. ​(Round to the nearest​ cent.)
​(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(102,000​) ​$(102,000​) 1    30,000            00 2   30,000            00 3   30,000            00 4    30,000            00 5    30,000   210,000 If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? The NPV of Project B is $nothing.​(Round to the nearest​ cent.)
YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -110,000 -110,000 1 30,000 0 2...
YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -110,000 -110,000 1 30,000 0 2 30,000 0 3 30,000 0 4 30,000 0 5 30,000 230,000 (Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 12 ​percent, which would be chosen and​ why?
Bruin, Inc., has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash...
Bruin, Inc., has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$37,000        –$37,000        1 19,000        6,000        2 14,500        12,500        3 12,000        19,000        4 9,000        23,000          a. What is the IRR for Project A?    b. What is the IRR for Project B?    c. If the required return is 11 percent, what is the NPV for Project A?    d. If...
Bruin, Inc., has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash...
Bruin, Inc., has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$37,000        –$37,000        1 19,000        6,000        2 14,500        12,500        3 12,000        19,000        4 9,000        23,000          a. What is the IRR for Project A?    b. What is the IRR for Project B?    c. If the required return is 11 percent, what is the NPV for Project A?    d. If...
You are considering two mutually exclusive projects that have been assigned the same discount rate of...
You are considering two mutually exclusive projects that have been assigned the same discount rate of 10.5 percent. Project A has an initial cost of $54,500, and should produce cash inflows of $16,400, $28,900, and $31,700 for Years 1 to 3, respectively. Project B has an initial cost of $79,400, and should produce cash inflows of $0, $48,300, and $42,100, for Years 1 to 3, respectively. What is the incremental IRR? 7.83% 5.40% −15.40% -4.67% 13.89%
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 -$50,000 -$50,000 1    15,000 0 2    15,000 0 3    15,000 0 4    15,000 0 5    15,000 99,000 If the required rate of return on these projects is 10 percent, which would be chosen and why?
Two projects being considered by a firm are mutually exclusive and have the following projected cash...
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows:      Year                               Project A                       Project B                                             Cash Flow                     Cash flow        0                                      (2000)                            (2000)        1                                         0                                     832        2                                         0                                     832        3                                         0                                     832        4                                       3877                                 832                                  Based only on the information given, which of the projects would be preferred and why? Mark the correct answer but justify your answer showing your computations. a.Project A, because it has...
Before whoever decides to answer the following problems, please DO NOT use excel. I have posted...
Before whoever decides to answer the following problems, please DO NOT use excel. I have posted this question already, and the expert answered using excel to solve this problem. I am not good with excel at all so I did not understand what was given. Would rather have the problem worked out showing the formula and work broken down and written out. Thank you in advance. You have been assigned the task of evaluating two mutually exclusive projects with the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT