Question

Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...

Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. Having a hard time coming up with the solution to this problem. (Do not round intermediate calculations and round your final answer to 2 decimal places.)

Project C

Time:

Cash flow: –    0          1          2       3         4      5

                     $2,000   $880 $780   $820 $500 $300

Should I accepted or rejected the problem?

Discounted payback period

years

Homework Answers

Answer #1

Ans 2.74 years

Year Project Cash Flows (i) DF@ 7% DF@ 7% (ii) PV of Project A ( (i) * (ii) ) Cumulative Cash Flow
0 -2000 1 1                             (2,000.00)                (2,000.00)
1 880 1/((1+7%)^1) 0.935                                  822.43                (1,177.57)
2 780 1/((1+7%)^2) 0.873                                  681.28                   (496.29)
3 820 1/((1+7%)^3) 0.816                                  669.36                     173.08
4 500 1/((1+7%)^4) 0.763                                  381.45                     554.52
5 300 1/((1+7%)^5) 0.713                                  213.90                     768.42
NPV                                  768.42
Discounted Payback Period = 2 years + 496.29/669.36
2.74 years
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.)      Project C   Time: 0 1 2 3 4 5   Cash flow –$2,400 $1,040 $900 $940 $580 $380      Discounted payback period years    Should the project be accepted or rejected? Accepted Rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,300 $600 $570 $610 $360 $160 Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,300 $1,000 $870 $910 $560 $360 Discounted payback period    years
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,000 $480 $480 $520 $300 $100
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,600 $1,120 $960 $1,000 $620 $420
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: −$1,400 $640 $600 $640 $380 $180
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: −$11,800 $3,430 $4,340 $1,680 $0 $1,160 Should the project be accepted or rejected? accepted rejected
Compute the payback statistic for Project A if the appropriate cost of capital is 9 percent...
Compute the payback statistic for Project A if the appropriate cost of capital is 9 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow: −$3,000 $1,150 $1,080 $920 $700 $500 Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,900 $840 $750 $790 $480 $280
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,700 $1,160 $990 $1,030 $640 $440