Question

Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...

Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results:

Economic Scenario Probability of Outcome NPV
Recession 0.05 ($42 million)
Below average 0.20 (26 million)
Average 0.50 12 million
Above average 0.20 24 million
Boom 0.05 34 million

Calculate the project's expected NPV, standard deviation, and coefficient of variation. Round your answers to two decimal places. Enter your answers for the project's expected NPV and standard deviation in millions. For example, an answer of $13,000,000 should be entered as 13.

E(NPV) = $ million
σNPV = $ million
CV =

Homework Answers

Answer #1

E(NPV)

$5.20 Million

σNPV

$21.01Million

CV

4.04

Project's expected NPV - E(NPV)

E(NPV) = Sum[NPV x Probability of Outcome]

= Sum[(-$42 x 0.05) + (-$26 x 0.20) + ($12 x 0.50) + ($24 x 0.20) + ($34 x 0.05)]

= -$2.10 - $5.20 + $6.00 + $4.80 + $1.70

= $5.20 Million

“E(NPV) = $5.20 Million”

Projects Standard Deviation - σNPV

σNPV = √[{0.05(-42 – 5.20)2} + {0.20(-26 – 5.20)2} + {0.50(12 – 5.20)2} + {0.20(24 – 5.20)2} + {0.05(34 – 5.20)2}]

= √[ 111.39 + 194.69 + 23.12 + 70.69 + 41.47

= √441.36

= $21.01 Million

“σNPV = $21.01Million”

Coefficient of Variation - CV

CV = σNPV / E(NPV)

= $21.01 Million / $5.20 Million

= 4.04

“CV = 4.04”

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($90 million) Below average 0.20 (24 million) Average 0.50 12 million Above average 0.20 14 million Boom 0.05 40 million Calculate the project's expected NPV, standard deviation, and coefficient...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario   Probability of Outcome   NPV Recession   0.05   ($42 million) Below average   0.20   (24 million) Average   0.50   12 million Above average   0.20   14 million Boom   0.05   38 million Calculate the project's expected NPV, standard deviation, and coefficient...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($34 million) Below average 0.20 (16 million) Average 0.50 12 million Above average 0.20 16 million Boom 0.05 38 million Calculate the project's expected NPV, standard deviation, and coefficient...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($48 million) Below average 0.20 (16 million) Average 0.50 12 million Above average 0.20 22 million Boom 0.05 28 million Calculate the project's expected NPV, standard deviation, and coefficient...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($38 million) Below average 0.20 (16 million) Average 0.50 12 million Above average 0.20 24 million Boom 0.05 40 million Calculate the project's expected NPV, standard deviation, and coefficient...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($78 million) Below average 0.20 (22 million) Average 0.50 12 million Above average 0.20 24 million Boom 0.05 32 million Calculate the project's expected NPV, standard deviation, and coefficient...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($30 million) Below average 0.20 (18 million) Average 0.50 12 million Above average 0.20 14 million Boom 0.05 36 million Calculate the project's expected NPV, standard deviation, and coefficient...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($42 million) Below average 0.20 (20 million) Average 0.50 12 million Above average 0.20 20 million Boom 0.05 26 million Calculate the project's expected NPV, standard deviation, and coefficient...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($86 million) Below average 0.20 (28 million) Average 0.50 12 million Above average 0.20 14 million Boom 0.05 34 million Calculate the project's expected NPV, standard deviation, and coefficient...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes...
Huang Industries is considering a proposed project whose estimated NPV is $12 million. This estimate assumes that economic conditions will be "average." However, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results: Economic Scenario Probability of Outcome NPV Recession 0.05 ($46 million) Below average 0.20 (26 million) Average 0.50 12 million Above average 0.20 14 million Boom 0.05 32 million Calculate the project's expected NPV, standard deviation, and coefficient...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT