Question

FDG company is deciding on a project investment. The project costs $91737. In year one, theres...

FDG company is deciding on a project investment. The project costs $91737. In year one, theres no cash flow due to construction. At end of year two, theres a $17352 cash flow. At end of year three, theres a $13482 cash flow. At end of year four, theres a $27473 cash flow. At end of year five, the project has a usage value of $20000 growing at 3% per year indefinitely. Discount rate is 9%. Calculate the npv of the project.

Homework Answers

Answer #1

Let us first find horizon value at end of year 5

horizon value at end of year 5 = usage value of year 6/Required rate of return - growth rate

growth rate = 3%

Required rate of return = 9%

usage value of year 6 = usage value of year 5(1+ growth rate)

= 20000(1+3%)

= 20000(1.03)

= 20600

Thus horizon value at end of year 5 = 20600/ 9%- 3%

=20600/6%

=343333.33$

Statement showing NPV

Year Cash flow PVIF @ 9% PV
1 0 0.9174 0.00
2 17352 0.8417 14604.83
3 13482 0.7722 10410.58
4 27473 0.7084 19462.57
5 20000 0.6499 12998.63
Horizon value 343333.33 0.6499 223143.11
Total of PV of cash inflow 280619.71
Less : Initial cash outflow 91737
NPV 188882.71

Thus NPV = 188,882.71 $

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The Company is considering a new project of 3 years. The initial investment on the the...
The Company is considering a new project of 3 years. The initial investment on the the machine costs $380,190, and will be depreciated on a straight-line basis to zero over the project life. The machine will become worthless in the end. The project will brings in annual operating cash flow of $220,110. It also requires an additional investment in net working capital of $4,000 initially, which will be fully recovered at the end of the project. The tax rate is...
A company is considering a new four-year project with an initial equipment investment of $72,001. The...
A company is considering a new four-year project with an initial equipment investment of $72,001. The equipment belongs in a 30% CCA class and will be worthless at the end of the project. Annual cash sales are estimated at $136,800 with annual cash costs of $87,901. The tax rate is 34%. What is the project cash flow in the second year? options: $30,900 $28,506 $38,516 $20,394 $41,406
The Rodriguez Company is considering an average-risk investment in a mineral water spring project that has...
The Rodriguez Company is considering an average-risk investment in a mineral water spring project that has a cost of $160,000. The project will produce 750 cases of mineral water per year indefinitely. The current sales price is $145 per case, and the current cost per case is $110. The firm is taxed at a rate of 36%. Both prices and costs are expected to rise at a rate of 6% per year. The firm uses only equity, and it has...
Lakonishok Equipment has an investment opportunity in Europe. The project costs €14 million and is expected...
Lakonishok Equipment has an investment opportunity in Europe. The project costs €14 million and is expected to produce cash flows of €3.3 million in year 1, €3.7 million in year 2, and €3.9 million in year 3. The current spot exchange rate is $1.25/€; the current risk-free rate in the United States is 5.2 percent, compared to that in Europe of 4.3 percent. The appropriate discount rate for the project is estimated to be 9 percent, the U.S. cost of...
You are planning to undertake an investment that costs $17,000 today. Once implemented, you estimate a...
You are planning to undertake an investment that costs $17,000 today. Once implemented, you estimate a 0.6 probability that it will do really well and bring in cash flows of $7,000 per year, a 0.3 probability that it will do moderately well and bring in a cash flow of $4,000 per year, and a 0.1 probability that it will limp along and bring in a cash flow of $2,000 a year. The discount rate or the opportunity cost of other...
Lakonishok Equipment has an investment opportunity in Europe. The project costs €15 million and is expected...
Lakonishok Equipment has an investment opportunity in Europe. The project costs €15 million and is expected to produce cash flows of €1.7 million in year 1, €3.4 million in year 2, and €2.7 million in year 3. The current spot exchange rate is $1.15/€; the current risk-free rate in the United States is 4.9 percent, compared to that in Europe of 4.8 percent. The appropriate discount rate for the project is estimated to be 17 percent, the U.S. cost of...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at start of​ project: ​$11,700,000 Cash flow at end of year​ one: ​$2,106,000 Cash flow at end of years two through​ six: ​$2,340,000 each year Cash flow at end of years seven through​ nine: ​$2,527,200 each year Cash flow at end of year​ ten: ​$1,805,143 Risky Business wants to know the payback​ period, NPV,​ IRR, MIRR, and PI of this project. The appropriate discount rate...
Growth Enterprises believes its latest project, which will cost $84,000 to install, will generate a perpetual...
Growth Enterprises believes its latest project, which will cost $84,000 to install, will generate a perpetual growing stream of cash flows. Cash flow at the end of the first year will be $9,000, and cash flows in future years are expected to grow indefinitely at an annual rate of 4%. a. If the discount rate for this project is 10%, what is the project NPV? (Do not round intermediate calculations.)   NPV $    b. What is the project IRR? (Do not...
A firm is evaluating a four-year project that requires an investment today of $2.6 million. In...
A firm is evaluating a four-year project that requires an investment today of $2.6 million. In addition, the project will require a one-time injection of working capital of $222,000 today that will be recovered at project end. The project is estimated to provide operating cash flows of $615,000 each year for the four years. The firm’s discount rate is 8.5%. What is the NPV of the project?
Inflation Adjustments The Rodriguez Company is considering an average-risk investment in a mineral water spring project...
Inflation Adjustments The Rodriguez Company is considering an average-risk investment in a mineral water spring project that has a cost of $160,000. The project will produce 900 cases of mineral water per year indefinitely. The current sales price is $140 per case, and the current cost per case is $106. The firm is taxed at a rate of 38%. Both prices and costs are expected to rise at a rate of 5% per year. The firm uses only equity, and...