Question

A stand-alone capital project has the following projected cash flows: Year 0 1 2 3 Cash...

A stand-alone capital project has the following projected cash flows:

Year 0 1 2 3 Cash flow ($4,000) $1,500 $1,200 $2,395

If the firm's cost of capital is 14%, which of the following statements is true?

a.the IRR is greater than the cost of capital and the project should be undertaken
b.the project should be rejected because the IRR is 12%, which is less than the project's cost of capital
c.the IRR is less than 12% and the project should be undertaken
d.the NPV of the project is positive and the project should be undertaken

Homework Answers

Answer #1

Cash Flows:
Year 0 = -$4,000
Year 1 = $1,500
Year 2 = $1,200
Year 3 = $2,395

Cost of Capital = 14%

NPV = -$4,000 + $1,500/1.14 + $1,200/1.14^2 + $2,395/1.14^3
NPV = -$144.29

Let IRR be i%

NPV = -$4,000 + $1,500/(1+i) + $1,200/(1+i)^2 + $2,395/(1+i)^3
0 = -$4,000 + $1,500/(1+i) + $1,200/(1+i)^2 + $2,395/(1+i)^3

Using financial calculator, i = 12%

Therefore, the project should be rejected because the IRR is 12%, which is less than the project's cost of capital.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow...
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow 0 ? 1 $2,000 2 3,000 3 3,000 4 1,500 The project has an IRR of 17% . The firm's cost of capital is 11 percent. What is the project's net present value (NPV)?
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. Group of answer choices The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be. If a project's NPV is less than zero, then its IRR must be less than the cost of capital. If a project's NPV is greater than zero, then its IRR must...
If you assume that a project being considered has normal cash flows, with one outflow followed...
If you assume that a project being considered has normal cash flows, with one outflow followed by a series of inflows, which statement would be correct? Question 11 options: a) The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be. b) If a project's NPV is less than zero, then its IRR must be less than the cost of capital. c) A project’s NPV is found by compounding the cash inflows...
Answer Question 1-3 Project A has the following projected cash flows: Year           Cash Flow 0                -11,23
Answer Question 1-3 Project A has the following projected cash flows: Year           Cash Flow 0                -11,235 1                4,400 2                4,400 3                4,400 4                4,400 5                7,400 Q1) The NPV of the above project is $_____. Assume a discount rate of 6%. a)9541 b)20776 c)17623 d)6388 Q2) The IRR for the above project is __ %. a)21.09 b)26.76 c)33.95 d)31.25 Q3)Which of the following statement is correct? a)If the discount rate increases, the IRR will decrease. b)If the discount rate increases, the NPV will stay the same. c)If...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. The NPVs of relatively risky projects should be found using relatively low costs of capital. b. If a project's NPV is greater than zero, then its IRR must be less than the cost of capital. c. The higher the cost of capital used to calculate the NPV, the lower the calculated NPV will...
​RiverRocks, Inc., is considering a project with the following projected free cash​ flows: Year 0 1...
​RiverRocks, Inc., is considering a project with the following projected free cash​ flows: Year 0 1 2 3 4 Cash Flow ​(in millions) −$49.3 $10.6 $20.8 $19.7 $15.8 The firm believes​ that, given the risk of this​ project, the WACC method is the appropriate approach to valuing the project.​RiverRocks' WACC is 11.5%. Should it take on this​ project? Why or why​ not? The timeline for the​ project's cash flows​ is: ​(Select the best choice​ below.) A.The timeline starts at Year...
Sam Corp. is considering a project that has the following cash flow data.  What is the project's...
Sam Corp. is considering a project that has the following cash flow data.  What is the project's IRR (Internal Rate of Return)? Note that a project's projected IRR can be less than the weighted average cost of capital (WACC) or negative, in both cases it will be rejected. Show work. Year                           0                1                2               3           4   Cash flows            -$1,900        $600          $825           $950   -$50 Helmand Inc. is considering a project that has the following cash flow and WACC data.  What is the project's MIRR?  Note that a project's projected MIRR can be less than...
Kiley Electronics is considering a project that has the following cash flow data. What is the...
Kiley Electronics is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's IRR can be less than the cost of capital (and even negative), in which case it will be rejected. Year 0 1 2 3 Cash flows −$1,100 $450 $470 $490
Datta Computer Systems is considering a project that has the following cash flow data. What is...
Datta Computer Systems is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's projected IRR can be less than the WACC (and even negative), in which case it will be rejected. Year       0   1 2 3   Cash flows          -$1,050 $450      $470      $490
​RiverRocks, Inc., is considering a project with the following projected free cash​ flows: Year 0 1...
​RiverRocks, Inc., is considering a project with the following projected free cash​ flows: Year 0 1 2 3 4 Cash Flow ​(in millions) −$50.6 $10.9 $19.8 $19.4 $14.6 The firm believes​ that, given the risk of this​ project, the WACC method is the appropriate approach to valuing the project.​ RiverRocks' WACC is 12.1%. Should it take on this​ project? Why or why​ not? The timeline for the​ project's cash flows​ is: ​(Select the best choice​ below.) A.The timeline starts at...