1. Given is a PERT project network diagram as shown below:
Activity |
Start |
A |
B |
C |
D |
E |
F |
G |
H |
I |
J |
K |
End |
Time |
0 |
18 |
24 |
21 |
38 |
28 |
34 |
22 |
20 |
34 |
34 |
16 |
0 |
1) | |||||
a) The Project completion time = total of all activities = 289 | |||||
b) ES of Activity F = total A to E = 129 | |||||
c) ES of Activity K = total A to K = 273 | |||||
d) LS of Activity E = (total K to F) + Time of Activity E = 160 + 28 = 188 | |||||
(LS is recorded going reverse from End) | |||||
WORKING NOTE: | |||||
Activity | Time | Total upto | |||
A | 18 | ||||
B | 24 | ||||
C | 21 | ||||
D | 38 | ||||
E | 28 | 129 | A to E | ||
F | 34 | 160 | K to F | ||
G | 22 | ||||
H | 20 | ||||
I | 34 | ||||
J | 34 | 273 | A to J | ||
K | 16 | ||||
TOTAL | 289 |