Question

1. Given is a PERT project network diagram as shown below: Activity Start A B C...

1. Given is a PERT project network diagram as shown below:

Activity

Start

A

B

C

D

E

F

G

H

I

J

K

End

Time

0

18

24

21

38

28

34

22

20

34

34

16

0

  

  1. a) The Project Completion time =  
    b) The Earliest Start time, ES, of Activity F =  
    c) The Earliest Start time, ES, of Activity K =  
    d) The Latest Start time, LS, of Activity E =  
    e) The non-critical activities are =  (ex. type in critical activities as ABCD, no comma, no space)

Homework Answers

Answer #1
1)
a) The Project completion time = total of all activities = 289
b) ES of Activity F = total A to E = 129
c) ES of Activity K = total A to K = 273
d) LS of Activity E = (total K to F) + Time of Activity E = 160 + 28 = 188
(LS is recorded going reverse from End)
WORKING NOTE:
Activity Time Total upto
A 18
B 24
C 21
D 38
E 28 129 A to E
F 34 160 K to F
G 22
H 20
I 34
J 34 273 A to J
K 16
TOTAL 289
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ___ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ____ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
The next set of questions use the following example: A network consists of the activities in...
The next set of questions use the following example: A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 3 C A 7 D A,B 3 E C 4 F D 6 Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. Find the total project completion time. What is the slack of activity B? 8 0 3 2 7
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times: Immediate Activity Predecessor Time A — 3 B — 4 C — 2 D A, B, C 2 E A, D 8 F C, D 7 G D, E 5 H F...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...