Question

There are two projects that the company is considering: Project A costs -10,000 to implement today,...

There are two projects that the company is considering:

Project A costs -10,000 to implement today, and it brings subsequent cash flows of 5,000 at the end of year 1;

1,500 at the end of year 2;

2,100 at the end of year 3;

and 3,400 at the end of year 4.

Project B's initial cost is -10,000, and subsequent cash flows are 2,500 per year for five (5) years.

WACC is 6% for both projects.

a. Calculate NPV and IRR for each project, and decide which one to recommend. Make sure to increase decimals in output cells if using Excel.

b. Calculate MIRR for projects A and B. Which project would you recommend based on MIRR?

c. Find the crossover rate. What does this rate represent? Describe in one sentence.

Homework Answers

Answer #1

a. Below is the calculation of NPV and IRR:

Hence, NPV of project A and B is $508.29 and $530.91 respectively. IRR of project A and B is 8.4% and 7.93% respectively.

As the NPV for project B is greater than project B, it will create more wealth. Hence, project B is recommened.

b.

Using 6% finance and re-investmnet rate MIRR for Project A and B is 7.32% and 7.1% respectively.

As, MIRR for project A is higher, firm should chose project B based on MIRR.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
There are 2 projects that the company is considering: Project A costs 10,000 to implement today,...
There are 2 projects that the company is considering: Project A costs 10,000 to implement today, and it brings subsequent cash flows of 5,000 at the end of year 1; 4,000 at the end of year 2; 6,000 at the end of year 3 Project B’s initial cost is 12,000, and subsequent cash flows are 6,000 per year for 3 years. WACC is 8% for both projects. a. calculate NPV and IRR for each project and decide which one to...
MIRR and NPV Your company is considering two mutually exclusive projects, X and Y, whose costs...
MIRR and NPV Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown below: Year X Y 0 -$5,000 -$5,000 1 1,000 4,500 2 1,500 1,500 3 2,000 1,000 4 4,000 500 The projects are equally risky, and their cost of capital is 15%. You must make a recommendation, and you must base it on the modified IRR (MIRR). Calculate the two projects' MIRRs. Do not round intermediate calculations. Round your answers...
Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows...
Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown below: Year X Y 0 -$5,000 -$5,000 1 1,000 4,500 2 1,500 1,500 3 2,000 1,000 4 4,000 500 The projects are equally risky, and their cost of capital is 11%. You must make a recommendation, and you must base it on the modified IRR (MIRR). Calculate the two projects' MIRRs. Do not round intermediate calculations. Round your answers to two decimal...
The Dark Blue Furniture Company is considering two mutually exclusive expansion projects. Project X will cost...
The Dark Blue Furniture Company is considering two mutually exclusive expansion projects. Project X will cost $20,000 to implement, and will generate $10,000 each year in positive net, after-tax cash flows for the next 3 years. Project Y will cost $3,000 to implement, and will generate $2,500 in net, after-tax cash flows for the next 3 years. The firm’s WACC is 9%. a. Calculate the net present value of each project. Which is preferable by the NPV method? b. Calculate...
Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows...
Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown below: Year X Y 0 -$5,000 -$5,000 1 1,000 4,500 2 1,500 1,500 3 2,000 1,000 4 4,000 500 The projects are equally risky, and their cost of capital is 14%. You must make a recommendation, and you must base it on the modified IRR (MIRR). Calculate the two projects' MIRRs. Round your answers to two decimal places. Project X % Project...
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen....
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1...
13. NPV and IRR Analysis Cummings Products Company is considering two mutually exclusive investments whose expected...
13. NPV and IRR Analysis Cummings Products Company is considering two mutually exclusive investments whose expected net cash flows are as follows: Expected Net Cash Flows Year Project A Project B 0 -$400 -$650 1 -528 210 2 -219 210 3 -150 210 4 1,100 210 5 820 210 6 990 210 7 -325 210 Select the correct graph for NPV profiles for Projects A and B.     The correct graph is (select one) graph __? What is each project's...
Projects A and B are mutually exclusive. Project A has cash flows of −$10,000, $5,100, $3,400,...
Projects A and B are mutually exclusive. Project A has cash flows of −$10,000, $5,100, $3,400, and $4,500 for Years 0 to 3, respectively. Project B has cash flows of −$10,000, $4,500, $3,400, and $5,100 for Years 0 to 3, respectively.          B-1 what is the IRR of project A?          B-2 What is the IRR of project B?          B-3 Based on the IRR rule, which project should be accepted and why?          B-4 At what required rate of...
Grey company is analyzing a project that requires an initial investment of $600,000. The project's expected...
Grey company is analyzing a project that requires an initial investment of $600,000. The project's expected cash flows are: (Year 1) $350,000, (Year 2) -$125,000, (Year 3) $500,000 and (Year 4) $400,000. 1. Grey company's WACC is 10%, and the project has the same risk as the firm's average project. Calculate this project's modified internal rate of return (MIRR): _______%. 2. If Grey company's managers select projects based on the MIRR criterion, they should accept or reject this independent project....
Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been...
Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 10%. 0 1 2 3 4 Project A -1,500 700...