Question

Please explain when do we have a conflict for the results produced by IRR and NPV...

Please explain when do we have a conflict for the results produced by IRR and NPV methods in evaluating a project and discuss the reasons for the conflict as well as a solution to eliminate the conflict.

Homework Answers

Answer #1

NPV and IRR, are two important measure of capital budgeting evaluation. NPV method provides result in term of Dollar as excess to value of investment and IRR method provides result in term of percentage as percentage return on initial investment.

Sometime NPV and IRR method provide conflicting result in term of acceptance of project. The reason behind this conflict is the assumed reinvestment rate. the NPV calculation implicitly assumes that intermediate cash flow is invested at cost of capital rate and IRR calculation assumes that the rate at which cash flow are reinvested is the IRR rate.

To eliminate this conflicting result the company either should use Net present value method to accept the project or use MIRR method.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other in the ranking of projects. List and explain three reasons why a conflict could exist. Which technique is best to use in a conflict? Explain.
IRR and NPV conflict Under what circumstances might the IRR and NPV approaches have conflicting results?
IRR and NPV conflict Under what circumstances might the IRR and NPV approaches have conflicting results?
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen....
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1...
I think that investors look at NPV and IRR (or any other data they are evaluating)...
I think that investors look at NPV and IRR (or any other data they are evaluating) as indicators of their own assessment of a project or investment.They can calculate the risk and return of the investment.When the investor finds out that his investment will bring negative NPV, he will cancel the investment. They will invest in the project when all the metrics are met. How do you think? Or do you have opposite view?
When given NPV, I have trouble understanding how IRR functions. I read some materials online, it...
When given NPV, I have trouble understanding how IRR functions. I read some materials online, it mentioned that the IRR (which is the discount rate) that makes NPV goes 0. Hence, for example: Year 0 1 2 3 4 Present Value (900) 247.72 282.78 366.06 17.77 NPV = 9.32 I understand we can use IRR function in excel, however, when I want to do it in an trial end error method, what formula should I insert my "guess" rate? Kindly...
The Basics of Capital Budgeting: NPV Profile A project's NPV profile graph intersects the Y-axis at...
The Basics of Capital Budgeting: NPV Profile A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's -Select-paybackMIRRIRRCorrect 1 of Item 1 (where NPV = 0). The Y-axis intersection point represents the project's undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the -Select-IRRpaybackMIRRCorrect 2 of Item 1 of the differences in the projects' cash...
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers...
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers could use the MIRR. It assumes reinvestment of projects' cash flows at the WACC, so it produces results consistent with NPV method. Let's try to find the MIRR for the project with the following cash flows: Initial cost of -800 at time zero, CF1 = 400, CF 2 = 570, CF3 = -130. Here we have two negative cash flows and two positive cash...
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from...
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from Project L are $15,000, while the undiscounted cash flows from Project S total $13,000. Their NPV profiles cross at a discount rate of 10 percent. Which of the following statements best describes this situation? Please leave an explanation.  a. The NPV and IRR methods will select the same project if the cost of capital is greater than 10 percent; for example, 18 percent. b. The...
Projects A and B are mutually exclusive and have the following cash flows: Year Project A...
Projects A and B are mutually exclusive and have the following cash flows: Year Project A Project B 0 -$82,000 -$82,000 1 34,000 0 2 34,000 0 3 34,000 108,000 1. What is the crossover rate? 2. Do we have a conflict in ranking between the NPV and IRR methods if the required rate of return is 8%? 3. Which project should be accepted if the required rate of return is 5%? 4. Which project should be accepted if the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT
Active Questions
  • IN PYTHON Add a while loop to this code so that it will replay the Game...
    asked 3 minutes ago
  • Build the subnetting tables for the following data (Classful addressing): IP: 192.44.82.16 Mask:255.255.255.192
    asked 11 minutes ago
  • If a future stream of payments is delayed, then the present value of that future stream...
    asked 17 minutes ago
  • Assume the random variable X is normally distributed with mean u=55 and standard deviation sigmaσequals=7. Compute...
    asked 17 minutes ago
  • John knows that monthly demand for his product follows a normal distribution with a mean of...
    asked 34 minutes ago
  • No one theory can account for all crimes. which theory of crime causation do you think...
    asked 44 minutes ago
  • Based on the below data: Customer1:Bread,Cereals,Milk Customer2:Tomatoes,Eggs Customer3:Pork,Bread,Milk Customer4:Sugar,Tomatoes,Pork,Bread Customer5:Vinegar Customer6:Eggs,Milk,Cereals,Sugar,Pork Customer7:Eggs,Milk,Vinegar Customer8:Sugar,Pork explain h
    asked 46 minutes ago
  • Pleas write a program that checks if any array of string is a plaindrome required input:...
    asked 52 minutes ago
  • A parallel-plate capacitor with plates of area 720 cm2 is charged to a potential difference V...
    asked 55 minutes ago
  • Develop an algorithm and a program in C that asks the user to enter a positive...
    asked 56 minutes ago
  • The principal of Paul Revere High School bragged that his 2016 graduating class of 1500 students...
    asked 58 minutes ago
  • Height is normally distributed with a mean of 68 inches and a standard deviation of 3...
    asked 58 minutes ago