Question

NPV Your division is considering two projects with the following cash flows (in millions): 0 1...

NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$20 $5 $9 $12 Project B -$13 $8 $7 $3 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Project A $ 5 million Project B $ 8 million What are the projects' NPVs assuming the WACC is 10%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Project A $ million Project B $ million What are the projects' NPVs assuming the WACC is 15%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Project A $ million Project B $ million What are the projects' IRRs assuming the WACC is 5%? Round your answer to two decimal places. Project A % Project B % What are the projects' IRRs assuming the WACC is 10%? Round your answer to two decimal places. Project A % Project B % What are the projects' IRRs assuming the WACC is 15%? Round your answer to two decimal places. Project A % Project B % If the WACC were 5% and A and B were mutually exclusive, which would you choose? (Hint: The crossover rate is 3.86%.) If the WACC were 10% and A and B were mutually exclusive, which would you choose? (Hint: The crossover rate is 3.86%.) If the WACC were 15% and A and B were mutually exclusive, which would you choose? (Hint: The crossover rate is 3.86%.)

Homework Answers

Answer #1

NPV of Both Project at Different discount rate is calculated in excel and screen shot provided below:

At 5% discount rate, NPV of project A is $3.29 and NPV of project B is $3.56.

At 10% discount rate, NPV of project A is $1.00 and NPV of project B is $2.31.

At 15% discount rate, NPV of project A is -$0.96 and NPV of project B is $1.22.

b.

IRR calculation does not use discount rate. So, IRR value will be similar at all three discount rate. So, IRR of project is calculated in excel and screen shot provided below:

IRR of project A is 12.46% and IRR of project B is 21.49%.

c.

At 15% discount rate, NPV of project A is -$0.96 and NPV of project B is $1.22. at 15% discount rate, NPV of project B is higher than NPV of project A. So At 15% discount rate, project B should be accepted.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Your division is considering two projects with the following cash flows (in millions): 0 1 2...
Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$20 $5 $9 $12 Project B -$13 $8 $7 $3 What are the projects' NPVs assuming the WACC is 5%? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to two decimal places. Project A:...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$21 $14 $9 $3 Project B -$35 $20 $8 $15 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$29 $15 $13 $3 Project B -$16 $8 $3 $6 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A    $...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$11 $4 $7 $1 Project B -$20 $12 $5 $9 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A    $   million...
14. Your division is considering two projects with the following cash flows (in millions): 0 1...
14. Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$20 $5 $9 $12 Project B -$13 $8 $7 $3 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A    $   million...
Your division is considering two projects with the following cash flows (in millions): 0 1 2...
Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$20 $5 $9 $12 Project B -$13 $8 $7 $3 What are the projects' NPVs assuming the WACC is 5%? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to two decimal places. Project A:    $   million...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$27 $13 $17 $8 Project B -$25 $14 $11 $2 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A    $   million...
Your division is considering two projects with the following cash flows (in millions): 0 1 2...
Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$19 $8 $15 $17 Project B -$17 $11 $8 $6 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A $...
Your division is considering two projects with the following cash flows (in millions): 0 1 2...
Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$27 $13 $17 $8 Project B -$25 $14 $11 $2 What are the projects' NPVs assuming the WACC is 5%? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to two decimal places. Project A:    $   million...
eBook Problem Walk-Through Your division is considering two projects with the following cash flows (in millions):...
eBook Problem Walk-Through Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$20 $5 $9 $12 Project B -$13 $8 $7 $3 What are the projects' NPVs assuming the WACC is 5%? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to two decimal...