Question

An INDEPENDENT project costs $1,000,000 and will return cash flows of $300,000 for 4 years. If...


An INDEPENDENT project costs $1,000,000 and will return cash flows of $300,000 for 4 years.

If you knew the firm's cost of capital rate (discount rate), which of the following measures would you use to determine whether to clearly ACCEPT or REJECT the project?

Homework Answers

Answer #1

Initial Investment = Project Cost = $ 1000000, Annual Cash Flow = $ 300000 and Tenure of Project = 4 years

If the firm's cost of capital is known, then the NPV measure will be used to ACCEPT or REJECT the Project. If the cost of capital is assumed to be R%, then NPV will be calculated as shown below:

NPV = 300000 x (1/R) x [1-{1/(1+R)^(4)}] - 1000000

A Positive Value of NPV should lead to the project being accepted whereas a negative value of NPV should lead to the project being rejected.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Lepton Industries has a project with the following projected cash​ flows: Initial cost: $470,000 Cash flow...
Lepton Industries has a project with the following projected cash​ flows: Initial cost: $470,000 Cash flow year one: $120,000 Cash flow year two: $300,000 Cash flow year three: $193,000 Cash flow year four: $120,000 a. Using a discount rate of 11% for this project and the NPV​ model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 14%? c. Should the company accept or reject it...
A project that provides annual cash flows of $11,700 for nine years costs $63,000 today. What...
A project that provides annual cash flows of $11,700 for nine years costs $63,000 today. What is the NPV for the project if the required return is 8 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) At a required return of 8 percent, should the firm accept this project? Accept Reject What is the NPV for the project if the required return is 20 percent? (A negative answer should be indicated by...
A capital investment project requires an initial investment of $100 and generates positive cash flows, $50...
A capital investment project requires an initial investment of $100 and generates positive cash flows, $50 and $100, at the end of the first and second years, respectively. (There is no cash flow after the second year) The firm uses a hurdle rate of 15% for projects of similar risk. Determine whether you should accept or reject the project based on NPV. Determine whether you should accept or reject the project based on IRR. Determine whether you should accept or...
A project that provides annual cash flows of $12,500 for 8 years costs $65,000 today. At...
A project that provides annual cash flows of $12,500 for 8 years costs $65,000 today. At what discount rate would you be indifferent between accepting the project or rejecting it? If the required rate of return is 9%, what is the profitability index of this project?   
An investment project has the following cash flows: Initial investment of $1,000,000 and cash flows starting...
An investment project has the following cash flows: Initial investment of $1,000,000 and cash flows starting in the first year through year 4 of $300,000 each. If the required rate of return is 12% What is the present value for each cash flow? What is the NPV and what decision should be made using the NPV?
A project has cash flows of –$148,400, $42,500, $83,200, and $42,600 for Years 0 to 3,...
A project has cash flows of –$148,400, $42,500, $83,200, and $42,600 for Years 0 to 3, respectively. The required rate of return is 10 percent. Based on the internal rate of return of _____ percent for this project, you should _____ the project. options: 6.69; accept 11.12; accept 7.48; reject 7.48; accept 6.69; reject Thank you!!
Net present value. Quark Industries has a project with the following projected cash​ flows: Initial​ cost:...
Net present value. Quark Industries has a project with the following projected cash​ flows: Initial​ cost: ​$200,000 Cash flow year​ one: ​$23,000 Cash flow year​ two: ​$72,000 Cash flow year​ three: ​$157,000 Cash flow year​ four: ​$157,000 a.  Using a discount rate of 10​% for this project and the NPV​ model, determine whether the company should accept or reject this project. b.  Should the company accept or reject it using a discount rate of 14​%? c.  Should the company accept...
Net present value. Lepton Industries has a project with the following projected cash​ flows: Initial cost  ...
Net present value. Lepton Industries has a project with the following projected cash​ flows: Initial cost   Cash flow year one   Cash flow year two   Cash flow year three   Cash flow year four $463,000   $124,000   $240,000   $185,000   $124,000 a. Using a discount rate of 99​% for this project and the NPV​ model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 1717​%? c. Should the company accept...
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today. What...
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today. What is the NPV for the project if the required return is 7 percent? What is the NPV for the project if the required return is 19 percent? At what discount rate would you be indifferent between accepting the project and rejecting it?
A project has cash flows of –$148,400, $42,500, $83,200, and $42,600 for Years 0 to 3,...
A project has cash flows of –$148,400, $42,500, $83,200, and $42,600 for Years 0 to 3, respectively. The required rate of return is 6 percent. Based on the internal rate of return of _____ percent for this project, you should _____ the project. Multiple Choice 6.96; accept 6.55; accept 6.96; reject 6.55; reject 8.12; accept