Question

Which problem associated with IRR is corrected by using MIRR? A. IRR assumes the cash-flows received...

Which problem associated with IRR is corrected by using MIRR?

A. IRR assumes the cash-flows received are reinvested at the WACC

B. IRR assumes the cash-flows received are reinvested at the IRR

C. IRR assumes the cash-flows received are reinvested at the MIRR

D. IRR assumes the cash-flows received are reinvested at the risk-free rate

Homework Answers

Answer #1

B. IRR assumes the cash-flows received are reinvested at the IRR

The modified internal rate of return (MIRR) assumes that positive cash flows are reinvested at the firm's cost of capital, and that the initial outlays are financed at the firm's financing cost. By contrast, the traditional internal rate of return (IRR)assumes the cash flows from a project are reinvested at the IRR itself. The MIRR, therefore, more accurately reflects the cost and profitability of a project.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the...
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Fuzzy Button Clothing Company is analyzing a project that requires an initial investment of $500,000. The project’s...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Cold Goose Metal Works Inc. is analyzing a project that requires an initial investment of $500,000....
8. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
8. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation : Cute Camel Woodcraft Company is analyzing a project that requires an initial investment of $3,225,000....
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate...
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate equal to the project’s IRR. However, in reality, the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, using the modified IRR approach, you can make a more reasonable estimate of a project’s rate of return than the project’s IRR can. Consider the following situation: Cold Goose Metal Works Inc. is analyzing a project that requires an initial investment...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $400,000. The project’s expected cash flows are: Year...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $450,000. The project’s expected cash flows are: Year Cash...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $2,500,000....
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $3,225,000....
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $2,500,000. The project’s expected cash flows are: Year...
Which of the following statements is NOT CORRECT? a. The IRR method takes into account the...
Which of the following statements is NOT CORRECT? a. The IRR method takes into account the time value of money b. The IRR method values a dollar received today greater than a dollar that will be received until sometime in the future c. The IRR method takes into account the cash flows over a project’s full life d. The IRR method assumes that the cash flows to be received from a project are to be reinvested at the WACC