A project has the following cash flows.
C0 | C1 | C2 | C3 |
($770) | $290 | $530 | $236 |
Calculate an IRR for the project using an iterative technique. (Hint: Start by guessing 17%.) Do not round intermediate calculations. Round PVF values in intermediate calculations to four decimal places. Round the answer to whole percentage.
%
The IRR is the rate at which NPV is zero.
Lets compute NPV at 17% as shown below:
= - $ 770 + $ 290 / 1.17 + $ 530 / 1.172 + $ 236 / 1.173
= $ 12.3864 Approximately
Lets compute NPV at 18.50% as shown below:
= - $ 770 + $ 290 / 1.1850 + $ 530 / 1.18502 + $ 236 / 1.18503
= - $ 6.02 Approximately
It means that the IRR lies between 17% and 18.50% and is computed as follows:
= Lower rate + [ Lower rate NPV / ( Lower rate NPV - Higher rate NPV ) ] x ( Higher rate - Lower rate)
= 17 + [ $ 12.3864 / ( $ 12.3864 - ( - $ 6.02) ] x ( 18.50 - 17)
= 17 + [ $ 12.3864 / $ 18.4064 ] x 1.50
= 17 + 1
= 18% Approximately
Feel free to ask in case of any query relating to this question
Get Answers For Free
Most questions answered within 1 hours.