Question

A project has the following cash flows. C0 C1 C2 C3 ($770) $290 $530 $236 Calculate...

A project has the following cash flows.

C0 C1 C2 C3
($770) $290 $530 $236

Calculate an IRR for the project using an iterative technique. (Hint: Start by guessing 17%.) Do not round intermediate calculations. Round PVF values in intermediate calculations to four decimal places. Round the answer to whole percentage.

%

Homework Answers

Answer #1

The IRR is the rate at which NPV is zero.

Lets compute NPV at 17% as shown below:

= - $ 770 + $ 290 / 1.17 + $ 530 / 1.172 + $ 236 / 1.173

= $ 12.3864 Approximately

Lets compute NPV at 18.50% as shown below:

= - $ 770 + $ 290 / 1.1850 + $ 530 / 1.18502 + $ 236 / 1.18503

= - $ 6.02 Approximately

It means that the IRR lies between 17% and 18.50% and is computed as follows:

= Lower rate + [ Lower rate NPV / ( Lower rate NPV - Higher rate NPV ) ] x ( Higher rate - Lower rate)

= 17 + [ $ 12.3864 / ( $ 12.3864 - ( - $ 6.02) ] x ( 18.50 - 17)

= 17 + [ $ 12.3864 / $ 18.4064 ] x 1.50

= 17 + 1

= 18% Approximately

Feel free to ask in case of any query relating to this question

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Here are the the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3...
Here are the the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A -21,200 9,328 9,328 9,328 B -21,200 0 0 28,620 what is the IRR of each project? (round answer to 2 decimal places)
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 22,200 +$ 9,768 +$ 9,768 +$ 9,768 B − 22,200 0 0 + 29,970 What is the IRR of each project? (Round your answers to 2 decimal places.)
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −6,950 4,700 18,400 a. Calculate...
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −6,950 4,700 18,400 a. Calculate the net present value of the above project for discount rates of 0, 50, and 100%. NPV @ 0% $ NPV @ 50% $ NPV @100% $ b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a percent rounded to the nearest whole number.) IRR %
Here are the cash flows for a project under consideration: C0 C1 C2 −$8,010 +$5,940 +$20,160...
Here are the cash flows for a project under consideration: C0 C1 C2 −$8,010 +$5,940 +$20,160 a. Calculate the project’s net present value for discount rates of 0, 50%, and 100%. (Round your answers to the nearest whole dollar.) b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a whole percent.)
Here are the cash flows for a project under consideration: C0 C1 C2 −$7,020 +$4,860 +$18,360...
Here are the cash flows for a project under consideration: C0 C1 C2 −$7,020 +$4,860 +$18,360 a. Calculate the project’s net present value for discount rates of 0, 50%, and 100%. (Round your answers to the nearest whole dollar.) b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a whole percent.)
Suppose the cash flows for project are C0 = -2000; C1 = 500; C2 = 1000;...
Suppose the cash flows for project are C0 = -2000; C1 = 500; C2 = 1000; C3 = 4000, C4= 1000, C5= 500. The discounted payback period is ____________________ and profitability index is ___________________ at a discount rate of 10 percent.
Given the following Cash flows: C0 = - $6,750 C1 = $4,500 C2 = $18,000 Calculate...
Given the following Cash flows: C0 = - $6,750 C1 = $4,500 C2 = $18,000 Calculate the NPV of the above project for discount rates of 0%, 50%, and 100%. What is the IRR of the project?
A project has the following forecasted cash flows: Cash Flows Thousands of dollars C0 C1 C2...
A project has the following forecasted cash flows: Cash Flows Thousands of dollars C0 C1 C2 C3 -100 40 60 50 The investor expected rate of return is 10%. The cost of capital is 12%. Required: 1.What will you choose to be the discount rate? Why? 2.Please calculate the payback period (PP) and return on investment (ROI). 3.Please calculate NPV,PVI and IRR.. 4.Make decision based on the above calculation and explain the reasons. 5.David said that the profit is the...
2. A project has the following cash flows             C0                    C1    &n
2. A project has the following cash flows             C0                    C1                    C2                    C3                                       ($1000)             $300                $400                $600 What is the project’s payback period? Year 0 1 2 3 Cash Flow ($1000) $300 $400 $600 Cumulative ($1000) ($700) ($300) 300 a. Calculate the projects NPV at 10%. b. Calculate the project’s PI at 10%. c. Calculate an IRR for the project in question 2 How would you answer a,b, and c in excel? I am getting...
The following cash flows are given for a project C0 = -9000 C1= +9000 C2= +18000...
The following cash flows are given for a project C0 = -9000 C1= +9000 C2= +18000 The NPV of the project at a discount rate of 50% is: A.) 18,000 B.) 5,000 C.) 11,000 D.) zero or E.) none of these The IRR for this project is: A.) 10% B.) 25% C.) 50% D.) 100% or E.) none of these The payback period for this project is: A.) zero years B.) one year C.) two years D.) three years or...