Question

To solve the bid price problem presented in the text, we set the project NPV equal...

To solve the bid price problem presented in the text, we set the project NPV equal to zero and found the required price using the definition of OCF. Thus the bid price represents a financial break-even level for the project. This type of analysis can be extended to many other types of problems.

      Martin Enterprises needs someone to supply it with 140,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost you $985,000 to install the equipment necessary to start production; you’ll depreciate this cost straight-line to zero over the project’s life. You estimate that, in five years, this equipment can be salvaged for $130,000. Your fixed production costs will be $560,000 per year, and your variable production costs should be $18.85 per carton. You also need an initial investment in net working capital of $120,000. Assume your tax rate is 25 percent and you require a return of 12 percent on your investment.

  

a.

Assuming that the price per carton is $29.00, what is the NPV of this project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

b. Assuming that the price per carton is $29.00, find the quantity of cartons per year you can supply and still break even. (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)
c. Assuming that the price per carton is $29.00, find the highest level of fixed costs you could afford each year and still break even. (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

Homework Answers

Answer #1

1.
=-985000+((140000*(29.00-18.85)-560000-985000/5)*(1-25%)+985000/5)/12%*(1-1/1.12^5)-120000+120000/1.12^5+130000*(1-25%)/1.12^5
=1523734.802

2.
Let quantity be Q
-985000+((Q*(29.00-18.85)-560000-985000/5)*(1-25%)+985000/5)/12%*(1-1/1.12^5)-120000+120000/1.12^5+130000*(1-25%)/1.12^5=0
=>Q=84473.055776

3.
Let fixed costs be F
-985000+((140000*(29.00-18.85)-F-985000/5)*(1-25%)+985000/5)/12%*(1-1/1.12^5)-120000+120000/1.12^5+130000*(1-25%)/1.12^5=0
=>F=1123598.483870

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
To solve the bid price problem presented in the text, we set the project NPV equal...
To solve the bid price problem presented in the text, we set the project NPV equal to zero and found the required price using the definition of OCF. Thus the bid price represents a financial break-even level for the project. This type of analysis can be extended to many other types of problems.       Romo Enterprises needs someone to supply it with 125,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve...
To solve the bid price problem presented in the text, we set the project NPV equal...
To solve the bid price problem presented in the text, we set the project NPV equal to zero and found the required price using the definition of OCF. Thus the bid price represents a financial break-even level for the project. This type of analysis can be extended to many other types of problems.       Martin Enterprises needs someone to supply it with 134,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve...
The technique for calculating a bid price can be extended to many other types of problems....
The technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 159,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...
The technique for calculating a bid price can be extended to many other types of problems....
The technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 157,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...
The technique for calculating a bid price can be extended to many other types of problems....
The technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 157,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...
The technique for calculating a bid price can be extended to many other types of problems....
The technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 159,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...
The technique for calculating a bid price can be extended to many other types of problems....
The technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 156,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...
he technique for calculating a bid price can be extended to many other types of problems....
he technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 153,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...
Calculating a Bid Price: Dahlia Enterprises needs someone to supply it with 120,000 cartons of machine...
Calculating a Bid Price: Dahlia Enterprises needs someone to supply it with 120,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost you $870,000 to install the equipment necessary to start production; you’ll depreciate this cost straight-line to zero over the project’s life. You estimate that, in five years, this equipment can be salvaged for $70,000. Your fixed production costs will be...
Guthrie Enterprises needs someone to supply it with 148,000 cartons of machine screws per year to...
Guthrie Enterprises needs someone to supply it with 148,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost you $1,880,000 to install the equipment necessary to start production; you’ll depreciate this cost straight-line to zero over the project’s life. You estimate that in five years, this equipment can be salvaged for $158,000. Your fixed production costs will be $273,000 per year, and...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT