Question

 Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​...

 Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​ firm's warehouse capacity. The relevant cash flows for the projects are shown in the following​ table:

LOADING...

. The​ firm's cost of capital is

1212​%.

a.  Calculate the IRR for each of the projects. Assess the acceptability of each project on the basis of the IRRs.

b.  Which project is​ preferred?

Initial investment

500000

320000

Year

1

130000

130000

2

130000

100000

3

170000

105000

4

180000

80000

5

250000

50000

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
William Industries is attempting to choose the better of two mutually exclusive projects for expanding the...
William Industries is attempting to choose the better of two mutually exclusive projects for expanding the firm’s production capacity. The relevant cash flows for the projects are shown in the following table. The firm’s cost of capital is 15%. PROJECT B PROJECT C YEAR Cash Flow Cash Flow 0 350000 50000 1 45000 24000 2 65000 22000 3 65000 19500 4 440000 14600 a) Calculate the period back of each project, assess its acceptability, and indicate which project is best,...
IRR: Mutually exclusive projects Ocean Pacific Restaurant is evaluating two mutually exclusive projects for expanding the...
IRR: Mutually exclusive projects Ocean Pacific Restaurant is evaluating two mutually exclusive projects for expanding the restaurant's seating capacity. The relevant cash flows for the projects are shown in the following table. The firm's cost of capital is 4%. Project X Project Y Initial Investment (CF) 980,000 363,000 Year               Cash inflows (CF) 1 150,000 110,000 2 170,000 98,000 3 220,000 93,000 4 270,000 82,000 5 340,000 67,000 a. calculate the IRR to the nearest whole percent for each of...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows Year Project Q Project R 0 $(4,000) $(4,000) 1 0 3,500 2 5,000 2,100 IRR 11.8% 28.40% If the firm's required rate of return (r) is 10 percent, which project should be purchased? a. Both projects should be purchased, because the IRRs for both projects exceed the firm's required rate of return. b. Neither project should be accepted, because their NPVs are too small...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows Year Project Q Project R 0 $(4,000) $(4,000) 1 0 3,500 2 5,000 2,100 IRR 11.8% 28.40% If the firm's required rate of return (r) is 10 percent, which project should be purchased? a. Both projects should be purchased, because the IRRs for both projects exceed the firm's required rate of return. b. Neither project should be accepted, because their NPVs are too small...
You are analyzing the following two mutually exclusive projects and have developed the following information. Please...
You are analyzing the following two mutually exclusive projects and have developed the following information. Please calculate the IRRs for the two projects and the crossover rate. Which project should you accept if the cost of capital is 5%, and which project should you accept if the cost of capital is 10%? Year Project A Cash Flow Project B Cash Flow 0 -$84,500 -$76,900 1 $29,000 $25,000 2 $40,000 $35,000 3 $27,000 $26,000 IRR A: ___________ IRR B: ___________ Crossover...
Briefly answer the questions that follow. You are considering two mutually exclusive projects. The NPV for...
Briefly answer the questions that follow. You are considering two mutually exclusive projects. The NPV for project one is positive and higher than the NPV for project two, while the IRR for project two is higher than that for project one. Which project should the firm accept and why? When does a project result in only one IRR? If a project has more than one IRR, how can we use Excel to find the multiple IRRs? A diversified, low-risk firm...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: The...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost of capital; answer the next 2 questions: year Project A Project B 0 -5000 -1000 1 2500 600 2 2500 600 3 2500 600 1)  Which project should be accepted, if any and why? A: Project B; it has a higher IRR and PI B: Neither project should be accepted, they both have negative NPVs C: Both project should be accepted; they have IRRs greater...
Bruins R Us is trying to choose between the following two mutually exclusive on-line game projects....
Bruins R Us is trying to choose between the following two mutually exclusive on-line game projects. Assume the discount rate for the company is 10 percent. Year A B IRR 26.67% 32.07% 0 -40,000 -15,000 1 21,000 8,500 2 21,000 8,500 3 21,000 8,500 Required: 1. Based on the IRR, which project should be accepted? What is main problem with IRR in the case? 2. Calculate the NPV of two projects. Based on the NPV, which project should be accepted?...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: Project...