The initial outlay of a 3-year project is $240,000. The project produces zero cash flows in the first two years and $325,000 in the third year. The discount rate used for this project is 8%. What is the estimated net present value for this project?
Calculate the net present value as follows:
Therefore, the net present value is $17,995.48.