Question

The initial outlay of a 3-year project is $240,000. The project produces zero cash flows in...

The initial outlay of a 3-year project is $240,000. The project produces zero cash flows in the first two years and $325,000 in the third year. The discount rate used for this project is 8%. What is the estimated net present value for this project?

Homework Answers

Answer #1

Calculate the net present value as follows:

Therefore, the net present value is $17,995.48.

Formulas:

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
AL-sahwa Inc. is considering a project with the following cash flows: Initial outlay = OMR 24,000....
AL-sahwa Inc. is considering a project with the following cash flows: Initial outlay = OMR 24,000. Cash flows for Year 1 = 50% of the Initial outlay; Year 2 = 60% of the Initial outlay and Year 3 = 35% of the Initial outlay. Calculate the net present value of the project, If the appropriate discount rate is 16%. Select one: a. OMR 4534 b. OMR 7466 c. OMR (7466) d. OMR 2428
1. A project has an initial outlay of $1,732. The project will generate annual cash flows...
1. A project has an initial outlay of $1,732. The project will generate annual cash flows of $783 over the 4-year life of the project and terminal cash flows of $258 in the last year of the project. If the required rate of return on the project is 4%, what is the net present value (NPV) of the project? Note: Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. 2.A...
A project has an initial outlay of $2,378. The project will generate annual cash flows of...
A project has an initial outlay of $2,378. The project will generate annual cash flows of $485 over the 5-year life of the project and terminal cash flows of $277 in the last year of the project. If the required rate of return on the project is 20%, what is the net present value (NPV) of the project? Note: Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box.
A company invests in a new project that requires an initial capital outlay of $835087. The...
A company invests in a new project that requires an initial capital outlay of $835087. The project will generate annual net cash flows of $196478 over a period of 9 years. The after-tax cost of capital is 10%. In addition, a working capital outlay of $55156 will be required. This working capital outlay will be recovered at the end of the project’s life. What is the net present value of the project? Select one: a. $264670 b. $296434 c. $933215...
A proposed project requires an initial cash outlay of $388,699 for equipment and an additional cash...
A proposed project requires an initial cash outlay of $388,699 for equipment and an additional cash outlay of $51,864 in year 1 to cover operating costs. During years 2 through 4, the project will generate cash inflows of $500,000 a year. What is the net present value of this project at a discount rate of 9 percent? Round your answer to the nearest whole dollar.
6c1 A project has an initial outlay of $2,154. It has a single cash flow at...
6c1 A project has an initial outlay of $2,154. It has a single cash flow at the end of year 8 of $4,834. What is the internal rate of return (IRR) for the project? Round the answer to two decimal places in percentage form. (Write the percentage sign in the "units" box) 6b1 Find the net present value (NPV) for the following series of future cash flows, assuming the company’s cost of capital is 14.71 percent. The initial outlay is...
A company is considering a 6-year project that requires an initial outlay of $18,000. The project...
A company is considering a 6-year project that requires an initial outlay of $18,000. The project engineer has estimated that the operating cash flows will be $4,000 in year 1, $7,000 in year 2, $7,000 in year 3, $7,000 in year 4, $7,000 in year 5, and $7,000 in year 6. At the end of the project, the equipment will be fully depreciated, classified as 5-year property under MACRS. The project engineer believes the equipment can be sold for $5,000...
If a project has an initial outlay of $41,000 and cash flows of $14,000 per year...
If a project has an initial outlay of $41,000 and cash flows of $14,000 per year for the next 5 years, what is the IRR of this project? (Answer to the nearest tenth of a percent, e.g. 12.3).
East Coast Television is considering a project with an initial outlay of​ $X (you will have...
East Coast Television is considering a project with an initial outlay of​ $X (you will have to determine this​ amount). It is expected that the project will produce a positive cash flow of $55,000 a year at the end of each year for the next 14 years. The appropriate discount rate for this project is 11 percent. If the project has an internal rate of return of 14 ​percent, what is the​ project's net present​ value? 1. If the project...
 East Coast Television is considering a project with an initial outlay of​ $X (you will have...
 East Coast Television is considering a project with an initial outlay of​ $X (you will have to determine this​ amount). It is expected that the project will produce a positive cash flow of ​$43000 a year at the end of each year for the next 14 years. The appropriate discount rate for this project is 7 percent. If the project has an internal rate of return of 9 ​percent, what is the​ project's net present​ value? a.  If the project...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT