Question

16. If a company's WACC is 10%, which of the following projects will be accepted? Select...

16. If a company's WACC is 10%, which of the following projects will be accepted? Select all that apply:

IRR = 8%

MIRR = 12%

NPV = $100,000

MIRR = 9%

14. As interest rates go up, which of the following is true? Select all that apply:

Bond Prices go down.

The NPV of a project goes down.

The NPV of a project goes up.

The NPV of a short term project goes down quicker than the NPV of a long term project.

Homework Answers

Answer #1

(16) Company's WACC = Cost of Capital = 10 %, IRR = 8 %, An IRR lower than the cost of capital is value erosive in nature, thereby being unacceptable. MIRR of 12 % entails that it is greater than the firm's cost of capital of 10 %(WACC) thereby being value accretive in nature. Hence, this project should be accepted. A positive NPV of $ 10000 is favourable and hence this project too should be accepted.

NOTE: Please raise separate queries for the solution to the remaining unrelated question.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$9,000 $3,000 $3,000 $3,000 $3,000 $3,000 Project N -$27,000 $8,400 $8,400 $8,400 $8,400 $8,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
Suppose William Inc. uses a WACC of 9% for below-average risk projects, 11% for average-risk projects,...
Suppose William Inc. uses a WACC of 9% for below-average risk projects, 11% for average-risk projects, and 13% for above-average risk projects. Which of the following independent projects should William accept, assuming that the company uses the NPV method when choosing projects? Project A, which has average risk and an IRR = 12%. Project B, which has below-average risk and an IRR = 9.5%. Project C, which has above-average risk and an IRR = 13.5%. Without information about the projects'...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$27,000 $9,000 $9,000 $9,000 $9,000 $9,000 Project N -$81,000 $25,200 $25,200 $25,200 $25,200 $25,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
Company B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y...
Company B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X. Years 0 1 2 3 Cash Flows -$100 $80 $60 $40 And the following information is available regarding Projects Y and Z. Criteria Project Y Project Z NPV $40 $67 MIRR 10% 20% IRR 6.5% 18.7% Regular Payback 2.23 years 1.77 years 1) If IRR for Project X is 17.95%, and the three project...
Which one of the following indicates a project should be accepted? A. NPV < 0 B....
Which one of the following indicates a project should be accepted? A. NPV < 0 B. IRR>WACC C. IRR<WACC D. NPV=1
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of...
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of return is 16%. Use this information for the next 3 questions. Year Project A Cash Flow Project B Cash Flow 0 ($50,000) ($20,000) 1 15,000 6,000 2 15,000 6,000 3 15,000 6,000 4 13,500 5,400 5 13,500 5,400 6 6,750 5,400 Which of the following statements is true concerning projects A and B? a) Due to time disparity, IRR indicates that project A should...
Puckett Inc. risk-adjusts its WACC to account for project risk. It uses a risk-adjusted project cost...
Puckett Inc. risk-adjusts its WACC to account for project risk. It uses a risk-adjusted project cost of capital of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects. Which of the following independent projects should Puckett accept, assuming that the company uses the NPV method when choosing projects? a. Project C, which has above-average risk and an IRR = 11%. b. Without information about the projects' NPVs we cannot determine which project(s) should be...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 The discounting rate (r)...
Which of the following statement is correct? Select one: a. All the answers are incorrect. b....
Which of the following statement is correct? Select one: a. All the answers are incorrect. b. A positive NPV means that the firm’s value will decrease if the project is adopted because the new project’s estimated return is lesst than the firm’s required rate of return. c. Reject the project if the IRR is greater than or equal to the required rate of return. d. Payback period is the discount rate that forces the NPV to equal zero. e. All...