Question

Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent....

Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project J Time: 0 1 2 3 4 5 Cash flow –$2,000 $650 $1,980 –$620 $600 –$200 MIRR % Should the project be accepted or rejected? Accepted Rejected

Homework Answers

Answer #1

Cost of Capital = 9%

Present Value of Cash Outflow = $2,000 + $620/1.09^3 + $200/1.09^5
Present Value of Cash Outflow = $2,608.74

Future Value of Cash Inflow = $650*1.09^4 + $1,980*1.09^3 + $600*1.09
Future Value of Cash Inflow = $4,135.69

MIRR = (Future Value of Cash Inflow / Present Value of Cash Outflow)^(1/n) - 1
MIRR = ($4,135.69 / $2,608.74)^(1/5) - 1
MIRR = 1.58532^(1/5) - 1
MIRR = 1.0965 - 1
MIRR = 0.0965
MIRR = 9.65%

So, we should accept this project.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Compute the MIRR statistic for Project J if the appropriate cost of capital is 8 percent....
Compute the MIRR statistic for Project J if the appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project J Time: 0 1 2 3 4 5 Cash flow: −$2,700 $860 $2,330 −$690 $810 −$270 Should the project be accepted or rejected? accepted rejected
compute the MIRR statistic for project I if the appropriate cost of capital is 13 percent...
compute the MIRR statistic for project I if the appropriate cost of capital is 13 percent (Do not round intermediate calculations and round your final answer to 2 decimal places) Project I Time 0 1 2 3 4 Cash flow -$11,500 $5,580 $4,430 $1,770 $2,250
Compute the MIRR statistic for Project I if the appropriate cost of capital is 11 percent....
Compute the MIRR statistic for Project I if the appropriate cost of capital is 11 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.)       Project I   Time: 0 1 2 3 4   Cash flow –$12,300 $5,980 $4,830 $2,170 $2,650
Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent....
Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 3 4 Cash flow: −$11,800 $3,750 $4,580 $1,920 $2,550 Should the project be accepted or rejected? rejected accepted
Compute the PI statistic for Project Q if the appropriate cost of capital is 11 percent....
Compute the PI statistic for Project Q if the appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)      Project Q   Time: 0 1 2 3 4   Cash flow –$12,300 $4,000 $4,830 $2,170 $2,800      PI       Should the project be accepted or rejected? Accepted Rejected
Compute the IRR statistic for Project F. The appropriate cost of capital is 11 percent. (Do...
Compute the IRR statistic for Project F. The appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 0 1 2 3 4 Cash flow: −$11,600 $4,150 $4,980 $2,320 $2,950 Should the project be accepted or rejected? accepted rejected
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$2,300 $670 $2,280 –$680 $620 –$260
Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent....
Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Z Time: 0 1 2 3 4 5 Cash flow: −$2,500 $650 $780 $950 $600 $400
Compute the payback statistic for Project A if the appropriate cost of capital is 9 percent...
Compute the payback statistic for Project A if the appropriate cost of capital is 9 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow: −$3,000 $1,150 $1,080 $920 $700 $500 Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,300 $600 $570 $610 $360 $160 Should the project be accepted or rejected? accepted rejected