Question

1)The modified IRR always leads to the same ranking decision as NPV for independent projects. TRUE...

1)The modified IRR always leads to the same ranking decision as NPV for independent projects.

TRUE OR FALSE?

2) Assume a project has normal cash flows, its NPV declines as the cost of capital increases.

TRUE OR FALSE?

Homework Answers

Answer #1

1. False.
Modified Internal rate of return is a better measure than normal IRR as the cash flows are compounded at the cost of capital and also the initial outflow is financed at the financing cost. On the other hand for IRR the reinvestment is done at the IRR itself.

Both NPV and MIRR would have different ranking if the nature of cash flows are different for the two projects. For example higher cash flow initially followed by lower in one and in the other the cash flow has a different nature then the NPV and MIRR will have different results.

2. True
According to present value formula, PV = cash flow /(1+wacc) , present value of cash flow decreases with increase in the cost of capital. Low Present value of cash inflows will lower the NPV, as NPV is calculated as PV of cash inflows - cash outflow.

Thus, lower the PV lower will be the NPV.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1(a). (TRUE or FALSE?) A project that has a positive NPV will also have an IRR...
1(a). (TRUE or FALSE?) A project that has a positive NPV will also have an IRR that is greater than the discount rate if the proposed capital budgeting projects are independent. 1(b). (TRUE or FALSE?) Projects with NPVs of positive values will reduce the firm’s value but it just meet the firm’s requirements.
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: The...
The Basics of Capital Budgeting: NPV Profile A project's NPV profile graph intersects the Y-axis at...
The Basics of Capital Budgeting: NPV Profile A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's -Select-paybackMIRRIRRCorrect 1 of Item 1 (where NPV = 0). The Y-axis intersection point represents the project's undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the -Select-IRRpaybackMIRRCorrect 2 of Item 1 of the differences in the projects' cash...
Project A has an IRR of 15%. Project B has an IRR of 13%. Both projects...
Project A has an IRR of 15%. Project B has an IRR of 13%. Both projects have a cost of capital of 12%. Which of the following statements would be correct? A. Both projects have a positive NPV. True or False? Explain B. Project A must have a higher NPV than Project B, True or False? Explain. C. If Project B has a higher NPV when cost of capital is 8%, then Project B must also have higher NPV if...
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen....
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1...
Capital Budgeting: 1. T/F If the NPV<0, the WACC > the IRR 2.T/F Salvage value is...
Capital Budgeting: 1. T/F If the NPV<0, the WACC > the IRR 2.T/F Salvage value is added back in to the last years projects cash flows 3. T/F NPV is considered to be the superior method for choosing capital budget projects 4. T/F If projects are mutually exclusive, if one has a higher IRR choose that project over the NPV decision. Cost of Capital 5. T/F external equity (new stock issuance) is less expensive since it will have a flotation...
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is...
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is 17%. The projects have the same risk and the same lives, and each has constant cash flows during each year of their lives. If the cost of capital is 10%, Project Y has a higher NPV than X. Given this information, which of the following statements is CORRECT? (Hint: it is useful to draw NPV profiles) The crossover rate must be less than 10%....
Discuss the following statement: If a firm has only independent projects, a constant WACC, and projects...
Discuss the following statement: If a firm has only independent projects, a constant WACC, and projects with normal cash flows, the NPV and IRR methods will always lead to identical capital budgeting decisions. What does this imply about the choice between IRR and NPV? If each of the assumptions were changed (one by one), how would you answer change?
Which of the following is not one of the benefits of using NPV over IRR to...
Which of the following is not one of the benefits of using NPV over IRR to judge a capital budgeting decision? IRR assumes that cash flows generated from the capital budgeting decision can be reinvested at the same rate of return as the project itself, NPV does not. NPV can be used to judge capital budgeting decisions with nonstandard cash flows, whereas IRR cannot. Unlike for IRR, the results from an NPV analysis can be easily compared to other capital...
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT