Question

Consider the following projects: Project C0 C1 C2 A − $ 2,850 + $ 2,750 +...

Consider the following projects:

Project C0 C1 C2
A $ 2,850 + $ 2,750 + $ 1,950
B 2,850 + 2,190 + 1,878

a. Calculate the profitability index for A and B assuming a 22% opportunity cost of capital.

Project A:

Project B:

Homework Answers

Answer #1

Project A:

Present value = Future value / (1 + rate)^time

Present value of cash flows = 2750 / (1 + 0.22)^1 + 1950 / (1 + 0.22)^2

Present value of cash flows = 2,254.098361 + 1,310.131685

Present value of cash flows = 3,564.230046

profitability index = Present value of cash flows / initial investment

profitability index = 3,564.230046 / 2850

profitability index = 1.25

Project B:

Present value = Future value / (1 + rate)^time

Present value of cash flows = 2,190 / (1 + 0.22)^1 + 1,878 / (1 + 0.22)^2

Present value of cash flows = 1,795.081967 + 1,261.757592

Present value of cash flows = 3,056.839559

profitability index = Present value of cash flows / initial investment

profitability index = 3,056.839559 / 2850

profitability index = 1.07

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project C0 C1 C2 A -2300 2200 1400 B -2300 1640 1768 Calculate the profitability index...
Project C0 C1 C2 A -2300 2200 1400 B -2300 1640 1768 Calculate the profitability index for A and B assuming a 25% opportunity cost of capital. (Do not round intermediate calculations. Round your answers to 4 decimal places.)
Consider the following projects: Cash Flows ($) Project C0 C1 D –10,900 21,800 E –20,900 36,575...
Consider the following projects: Cash Flows ($) Project C0 C1 D –10,900 21,800 E –20,900 36,575 Assume that the projects are mutually exclusive and that the opportunity cost of capital is 8%. a. Calculate the profitability index for each project. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project Profitability Index D E b-1. Calculate the profitability-index using the incremental cash flows. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Profitability-index b-2....
Consider the following projects: Cash Flows ($) Project C0 C1 D –11,300 22,600 E –21,300 37,275...
Consider the following projects: Cash Flows ($) Project C0 C1 D –11,300 22,600 E –21,300 37,275 Assume that the projects are mutually exclusive and that the opportunity cost of capital is 9%. a. Calculate the profitability index for each project. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project Profitability Index D E b-1. Calculate the profitability-index using the incremental cash flows. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Profitability-index b-2....
Suppose the cash flows for project are C0 = -2000; C1 = 500; C2 = 1000;...
Suppose the cash flows for project are C0 = -2000; C1 = 500; C2 = 1000; C3 = 4000, C4= 1000, C5= 500. The discounted payback period is ____________________ and profitability index is ___________________ at a discount rate of 10 percent.
Here are the the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3...
Here are the the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A -21,200 9,328 9,328 9,328 B -21,200 0 0 28,620 what is the IRR of each project? (round answer to 2 decimal places)
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 22,200 +$ 9,768 +$ 9,768 +$ 9,768 B − 22,200 0 0 + 29,970 What is the IRR of each project? (Round your answers to 2 decimal places.)
Consider projects A and B: Cash Flows (dollars) Projects A B C0 450,000 320,000 C1 310,000...
Consider projects A and B: Cash Flows (dollars) Projects A B C0 450,000 320,000 C1 310,000 80,000 C2 120,000 100,000 C3 85,000 250,000 What is the NPV at 10% required rate? Which is the best Project?
Consider projects A and B: Cash Flows (dollars) Projects A B C0 450,000 320,000 C1 310,000...
Consider projects A and B: Cash Flows (dollars) Projects A B C0 450,000 320,000 C1 310,000 80,000 C2 120,000 100,000 C3 85,000 250,000 What is the NPV at 10% required rate? Which is the best Project?
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −6,950 4,700 18,400 a. Calculate...
Consider the following cash flows: Cash Flows ($) C0 C1 C2 −6,950 4,700 18,400 a. Calculate the net present value of the above project for discount rates of 0, 50, and 100%. NPV @ 0% $ NPV @ 50% $ NPV @100% $ b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a percent rounded to the nearest whole number.) IRR %
Given the following Cash flows: C0 = - $6,750 C1 = $4,500 C2 = $18,000 Calculate...
Given the following Cash flows: C0 = - $6,750 C1 = $4,500 C2 = $18,000 Calculate the NPV of the above project for discount rates of 0%, 50%, and 100%. What is the IRR of the project?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT