Question

Project L costs $50,968.24, its expected cash inflows are $12,000 per year for 8 years, and...

Project L costs $50,968.24, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places.

Homework Answers

Answer #1
Project's IRR is the rate at which Net present value of project is 0.
Year Cash flows
0 $ -50,968.24
1 12000
2 12000
3 12000
4 12000
5 12000
6 12000
7 12000
8 12000
IRR = =irr(C4:C12)
= 16.70%
C4:C12 is the range of cash flows from year 0 to year 8.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project L costs $44,581.60, its expected cash inflows are $10,000 per year for 9 years, and...
Project L costs $44,581.60, its expected cash inflows are $10,000 per year for 9 years, and its WACC is 13%. What is the project's IRR? Round your answer to two decimal places. Project L costs $50,000, its expected cash inflows are $12,000 per year for 7 years, and its WACC is 10%. What is the project's payback? Round your answer to two decimal places.
Project L costs $60,106.33, its expected cash inflows are $12,000 per year for 11 years, and...
Project L costs $60,106.33, its expected cash inflows are $12,000 per year for 11 years, and its WACC is 10%. What is the project's IRR? Round your answer to two decimal places. %
Project L costs $50,000, its expected cash inflows are $12,000 per year for 8 years, and...
Project L costs $50,000, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 12%. What is the project's discounted payback? Round your answer to two decimal places.
Project L costs $40,000, its expected cash inflows are $12,000 per year for 8 years, and...
Project L costs $40,000, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 14%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places.
a. Project L costs $42,220.68, its expected cash inflows are $9,000 per year for 11 years,...
a. Project L costs $42,220.68, its expected cash inflows are $9,000 per year for 11 years, and its WACC is 12%. What is the project's IRR? Round your answer to two decimal places. b.Project L costs $45,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 14%. What is the project's MIRR? Round your answer to two decimal places. Do not round your intermediate calculations. c. Project L costs $70,000, its expected cash inflows...
1. Project L costs $60,000, its expected cash inflows are $14,000 per year for 6 years,...
1. Project L costs $60,000, its expected cash inflows are $14,000 per year for 6 years, and its WACC is 9%. What is the project's payback? Round your answer to two decimal places. 2. Project L costs $40,955.09, its expected cash inflows are $9,000 per year for 10 years, and its WACC is 13%. What is the project's IRR? Round your answer to two decimal places.
1.Project K costs $57,890.94, its expected cash inflows are $14,000 per year for 8 years, and...
1.Project K costs $57,890.94, its expected cash inflows are $14,000 per year for 8 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places. 2.Project K costs $35,000, its expected cash inflows are $10,000 per year for 8 years, and its WACC is 9%. What is the project's discounted payback? Round your answer to two decimal places. 3.Project K costs $45,000, its expected cash inflows are $11,000 per year for 10 years,...
1. Project K costs $45,000, its expected cash inflows are $15,000 per year for 9 years,...
1. Project K costs $45,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 11%. What is the project's NPV? Round your answer to the nearest cent. 2. Project K costs $59,542.90, its expected cash inflows are $12,000 per year for 10 years, and its WACC is 14%. What is the project's IRR? Round your answer to two decimal places. 3. Project K costs $75,000, its expected cash inflows are $15,000 per year for...
Project L costs $42,791.88, its expected cash inflows are $9,000 per year for 9 years, and...
Project L costs $42,791.88, its expected cash inflows are $9,000 per year for 9 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places.
Project L costs $47,333.24, its expected cash inflows are $11,000 per year for 9 years, and...
Project L costs $47,333.24, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 13%. What is the project's IRR? Round your answer to two decimal places.