Question

Selecting the project(s) with the highest NPV(s) is not the correct decision rule when: Multiple Choice...

Selecting the project(s) with the highest NPV(s) is not the correct decision rule when: Multiple Choice

a. there is capital rationing.

b. there are mutually exclusive projects.

c. projects are long-lived.

d. projects are independent.

Homework Answers

Answer #1

Answer: Option "a" is correct.

In case of capital rationing there are restrictions on the capital that can be invested on new projects undertaken by a firm. This is due to limited availability of capital that can be invested. If a firm selects a project with highest NPV and higher required investment, then it might have to quit the project in between due to lesser availability of funds leading to huge loss.

Mutually exclusive projects are the set of projects out of which only one project can be accepted. Project with highest NPV should be accepted.
In case of long lived projects, the projects with highest NPV are accepted.
In case of independent projects, all the projects that meet the criteria of capital budgeting can be accepted. Projects with highest NPV are accepted.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following is not a net present value (NPV) decision rule? A        When choosing...
Which of the following is not a net present value (NPV) decision rule? A        When choosing among independent projects, select the one with the highest rate of return B        If an independent investment’s NPV is negative, reject the project C        If an independent investment’s NPV is positive, accept the project D        When choosing among mutually exclusive projects, select the one with the highest NPV
Multiple choice: The IRR system of project evaluation for selecting one of two mutually exclusive projects...
Multiple choice: The IRR system of project evaluation for selecting one of two mutually exclusive projects a) has the disadvantage or ignoring future cash flows, similar to that of the discounted payback period rule. b) may give different results from NV if the two projects have a different scale of investment and cash flow returns. c) should always be used in conjunction with the discounted payback system of project evaluation. d) always provides at least one value for the IRR...
Which one of the following is False when it comes to IRR? Multiple Choice It can...
Which one of the following is False when it comes to IRR? Multiple Choice It can be intuitively appealing because it presents its results as a percentage rather than a dollar amount It is not as reliable as NPV when looking at mutually exclusive projects It will always yield more than 1 result when NPV is negative It will always agree with NPV for projects where all cash flows beyond Year 0 are positive as long as the project is...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 The discounting rate (r)...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 1.00 2.25 1.92 The discounting rate...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.25 1.92 The discounting rate...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.25 1.92 The discounting rate...
When evaluating capital projects, the decisions using the NPV method and the IRR method will agree...
When evaluating capital projects, the decisions using the NPV method and the IRR method will agree if: a) the projects are independent. b) the cash flow pattern is conventional. c) the projects are mutually exclusive. d) both a and b.
) Which if the statements below describes the correct capital budgeting decision rule? a) Reject a...
) Which if the statements below describes the correct capital budgeting decision rule? a) Reject a project if the cost of capital exceeds the IRR. B) Reject a project if the cost of capital is less that the NPV. C) Accept a project if the NPV is greater than the IRR. D) Accept a project if the cost of capital is greater that the NPV.
19. Chapter b Multiple Choice 11-107, Section b Multiple Choice 11-107, Problem b Multiple Choice 11-107...
19. Chapter b Multiple Choice 11-107, Section b Multiple Choice 11-107, Problem b Multiple Choice 11-107 Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT