Question

A firm evaluates all of its projects by using the NPV decision rule. Year Cash Flow...

A firm evaluates all of its projects by using the NPV decision rule. Year Cash Flow 0 –$27,000 1 20,000 2 13,000 3 8,000 a. At a required return of 13 percent, what is the NPV for this project? b. At a required return of 33 percent, what is the NPV for this project?

A project that provides annual cash flows of $10,600 for 8 years costs $56,550 today.

  

a. If the required return is 7 percent, what is the NPV for this project?

  

b. Determine the IRR for this project.

Homework Answers

Answer #1

a

Project
Discount rate 13.000%
Year 0 1 2 3
Cash flow stream -27000 20000 13000 8000
Discounting factor 1.000 1.130 1.277 1.443
Discounted cash flows project -27000.000 17699.115 10180.907 5544.401
NPV = Sum of discounted cash flows
NPV Project = 6424.42
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

b

Project
Discount rate 33.000%
Year 0 1 2 3
Cash flow stream -27000 20000 13000 8000
Discounting factor 1.000 1.330 1.769 2.353
Discounted cash flows project -27000.000 15037.594 7349.200 3400.440
NPV = Sum of discounted cash flows
NPV Project = -1212.77
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

a

Project
Discount rate 7.000%
Year 0 1 2 3 4 5 6 7 8
Cash flow stream -56550 10600 10600 10600 10600 10600 10600 10600 10600
Discounting factor 1.000 1.070 1.145 1.225 1.311 1.403 1.501 1.606 1.718
Discounted cash flows project -56550.000 9906.542 9258.451 8652.757 8086.689 7557.654 7063.228 6601.147 6169.297
NPV = Sum of discounted cash flows
NPV Project = 6745.76
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

b

Project
IRR is the rate at which NPV =0
IRR 10.00%
Year 0 1 2 3 4 5 6 7 8
Cash flow stream -56550.000 10600.000 10600.000 10600.000 10600.000 10600.000 10600.000 10600.000 10600.000
Discounting factor 1.000 1.100 1.210 1.331 1.464 1.611 1.772 1.949 2.144
Discounted cash flows project -56550.000 9636.354 8760.314 7963.914 7239.915 6581.734 5983.389 5439.439 4944.940
NPV = Sum of discounted cash flows
NPV Project = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 10.00%
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A firm evaluates all of its projects by using the NPV decision rule. Year (Cash Flow)...
A firm evaluates all of its projects by using the NPV decision rule. Year (Cash Flow) Y0 (–$27,000) Y1 (22,000) Y2 (14,000) Y3 (8,000) a. At a required return of 26 percent, what is the NPV for this project? b. At a required return of 32 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule. Year                 Cash Flow...
A firm evaluates all of its projects by using the NPV decision rule. Year                 Cash Flow 0 –$25,000       1 22,000       2 13,000       3 8,000          Required: (a) At a required return of 23 percent, what is the NPV for this project?    (b) At a required return of 41 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash...
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash Flow 0 –$31,000       1 20,000       2 15,000       3 8,000          a. At a required return of 12 percent, what is the NPV for this project?    b. At a required return of 32 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash...
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash Flow 0 –$28,000       1 19,000       2 13,000       3 9,000          a. At a required return of 14 percent, what is the NPV for this project?    b. At a required return of 39 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash...
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash Flow 0 –$27,000       1 20,000       2 16,000       3 7,000          Required: (a) At a required return of 21 percent, what is the NPV for this project? (Click to select)4,232.12 4,320.29 4,628.88 ,408.464 4496.63    (b) At a required return of 34 percent, what is the NPV for this project? (Click to select) -259.78 -267.42 -244.5 -254.69 -249.6
A firm evaluates all of its projects by using the NPV decision rule Year Cash Flow...
A firm evaluates all of its projects by using the NPV decision rule Year Cash Flow 0 -31,000 1 23,000 2 13,000 3 11,000 At a required return of 17 percent, what is the NPV for this project? 5,023 $5,274 $4,822 $5,123 $4,922 b. At a required return of 34 percent, what is the NPV for this project? $-2,125.40 $-1,943.23 $-2,064.68 $-1,983.71 $-2,024.20
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash...
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash Flow 0 –$29,000       1 22,000       2 17,000       3 7,000          a. At a required return of 23 percent, what is the NPV for this project? b. At a required return of 33 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash...
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash Flow 0 –$29,000       1 20,000       2 14,000       3 10,000          a. At a required return of 19 percent, what is the NPV for this project?    b. At a required return of 34 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash...
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash Flow 0 –$29,000       1 20,000       2 16,000       3 5,000          a. At a required return of 25 percent, what is the NPV for this project? b. At a required return of 41 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash...
A firm evaluates all of its projects by using the NPV decision rule.    Year                 Cash Flow 0 –$31,000       1 21,000       2 12,000       3 5,000          a. At a required return of 15 percent, what is the NPV for this project? b. At a required return of 40 percent, what is the NPV for this project?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT