Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: –$12,500 $3,500 $4,480 $1,820 $0 $1,300 Should the project be accepted or rejected?
The correct answer is zero.
This is because the project never pays back
Year | Investment | Cash Inflow | Net Cash Flow | |
0 | -12,500.00 | - | -12,500.00 | (Investment + Cash Inflow) |
1 | - | 3,500 | -9,000.00 | (Net Cash Flow + Cash Inflow) |
2 | - | 4,480 | -4,520.00 | (Net Cash Flow + Cash Inflow) |
3 | - | 1,820 | -2,700.00 | (Net Cash Flow + Cash Inflow) |
4 | - | 0 | -2,700.00 | (Net Cash Flow + Cash Inflow) |
5 | - | 1,300 | -1,400.00 | (Net Cash Flow + Cash Inflow) |
Since the Project have a zero payback period, the project must be rejected.
Hence the correct answer is Rejected.
Get Answers For Free
Most questions answered within 1 hours.