Question

Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...

Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$3,100 $710 $840 $880 $960 $460

Should the project be rejected or accepted?

Homework Answers

Answer #1

Net Present Value [NPV] = Present Value of cash Inflows – Initial Investment

= $3,094.84 – 3,100

= - $5.16 [ Negative NPV ]

Present Value of cash Inflows

Year

Cash Flows

Present Value factor at 8%

Present Value of cash flows

1

0.92593

710

657.41

2

0.85734

840

720.17

3

0.79383

880

698.57

4

0.73503

960

705.63

5

0.68058

460

313.07

TOTAL

3094.84

Dicision

“ Since the NPV is Negative, The Project “ SHOULD BE REJECTED ”

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow –$2,200 $590 $720 $760 $840 $340 NPV $ Should the project be accepted or rejected?
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$1,200 $390 $520 $560 $640 $140 Problem 13-3 NPV with Non-normal Cash Flows (LG13-3) Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative...
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal place.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,300 $3,610 $4,440 $1,780 $560 NPV $ _________ Should the project be accepted or rejected? _____________
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$1,600 $590 $2,080 –$640 $540 –$220 NPV= Should the project be accepted or rejected?
Compute the NPV statistic for Project U if the appropriate cost of capital is 11 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$2,500 $750 $2,480 –$720 $700 –$300
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$2,300 $670 $2,280 –$680 $620 –$260
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)         Project E   Time: 0 1 2 3 4 5   Cash flow –$2,700 $830 $840 $760 $540 $340 IRR % ____________ Should the project be accepted or rejected? _________
Compute the MIRR statistic for Project J if the appropriate cost of capital is 8 percent....
Compute the MIRR statistic for Project J if the appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project J Time: 0 1 2 3 4 5 Cash flow: −$2,700 $860 $2,330 −$690 $810 −$270 Should the project be accepted or rejected? accepted rejected
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Time: 0 1 2 3 4 5 Cash Flow: -$1,800 $670 $720 $680 $460 $260 IRR _____________ % Should the project be accepted or rejected?
Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent....
Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 3 4 Cash flow: −$11,800 $3,750 $4,580 $1,920 $2,550 Should the project be accepted or rejected? rejected accepted
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT