Question

30) Internal Rate of Return is a tool Financial Analysts use to determine whether to accept...

30) Internal Rate of Return is a tool Financial Analysts use to determine whether to accept or reject a potential project the firm is considering. It is defined as:

Multiple Choice

  • the discount rate that results in a zero net present value (NPV) for the project.

  • the discount rate that results in a net present value (NPV) equal to the project's initial cost.

  • the discount rate that causes a project's after-tax income to equal zero.

  • the rate of return required by the project's investors.

  • the project's current market rate of return.

Homework Answers

Answer #1

Answer : Correct Option is the discount rate that results in a zero net present value (NPV) for the project.

Reason :

IRR is the discount rate at which present value of cash inflow is equal to present value of cash outflow, thus making Net present value zero. The IRR is to be obtained by hit and trial method to ascertain the discount rate at which , present value of cash inflow equals to present value of cash outflow.The use of IRR , as criterion to accept capital investment decision involves comparision of IRR with the required rate of return known as cut off rate . If IRR is greater than the cut off rate , the project should be accepted. If IRR is less than the cut off rate, the project is rejected. If IRR is equal to the cut off rate , the firm is indifferent.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following statements defines the internal rate of return (IRR) for a project? A....
Which of the following statements defines the internal rate of return (IRR) for a project? A. Discount rate which results in a zero NPV B. Discount rate which results in a NPV equal to the project's initial cost C. Rate of return required by the project's investors D. The current market rate of return for projects of similar risk
1. The internal rate of return identifies: A. the minimum acceptable discount rate. B. the cost-benefit...
1. The internal rate of return identifies: A. the minimum acceptable discount rate. B. the cost-benefit ratio. C. the average profit from a project. D. none of the given answers. 2. The net present value rule states that you should accept a project if the NPV: A. is equal to zero or negative. B. exceeds the required rate. C. is less than 1.0. D. is positive. 3. A net present value of zero implies that an investment: A. has an...
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
If a firm considers two separate projects but is only able to accept one of the...
If a firm considers two separate projects but is only able to accept one of the projects due to the fact that each project would require exclusive use of the Company’s manufacturing machinery, these projects are considered to be: Select one: a. Independent b. Interdependent c. Mutually exclusive d. Mutually inclusive e. Operationally distinct Internal rate of return (IRR) is defined as the: Select one: a. discount rate which causes the net present value of a project to equal zero....
Which of the following statements about internal rate of return (IRR) is false? explain why IRR...
Which of the following statements about internal rate of return (IRR) is false? explain why IRR is the discount rate at which the present value of future expected cash flows is exactly equal to the initial investment. The IRR rule always leads to the same decision as the NPV rule. IRR is the discount rate at which a project's NPV equals zero.
ALL OF THE BELOW ARE TRUE ABOUT INTERNAL RATE OF RETURN EXCEPT Select one: a. ACCEPT...
ALL OF THE BELOW ARE TRUE ABOUT INTERNAL RATE OF RETURN EXCEPT Select one: a. ACCEPT THE PROJECT IF IRR IS LESS THAN THE DISCOUNT RATE b. NPV EQUAL ZERO c. ACCEPT THE PROJECT IF IRR IS HIGHER THAN THE DISCOUNT RATE d. IRR IS A WAY TO EVALUATE THE ACCEPTANCE OF A PROJECT Please Solve As soon as Solve quickly I get you two UPVOTE directly Thank's Abdul-Rahim Taysir
When considering internal rate of return (IRR), which statement(s) is/are correct? I. The IRR method of...
When considering internal rate of return (IRR), which statement(s) is/are correct? I. The IRR method of analysis can be adapted to handle non-conventional cash flows. II. The IRR that causes the net present value of the differences between two project's cash flows to equal zero is called the crossover rate. III. The IRR tends to be used more than net present value simply because its results are easier to comprehend. IV. Both the timing and the amount of a project's...
Internal rate of return is calculated by: A. Finding the discount rate that forces the NPV...
Internal rate of return is calculated by: A. Finding the discount rate that forces the NPV of the project to zero. B. Adjusting the initial outlay of the project so that it is equal to the discounted cash flows. C. Adjusting the inflow until the NPV is zero. D. All of the above. E. None of the above.
East Coast Television is considering a project with an initial outlay of​ $X (you will have...
East Coast Television is considering a project with an initial outlay of​ $X (you will have to determine this​ amount). It is expected that the project will produce a positive cash flow of $55,000 a year at the end of each year for the next 14 years. The appropriate discount rate for this project is 11 percent. If the project has an internal rate of return of 14 ​percent, what is the​ project's net present​ value? 1. If the project...
If a project has a net present value equal to zero, then: Group of answer choices...
If a project has a net present value equal to zero, then: Group of answer choices the project earns a return exactly equal to the discount rate. the total of the cash inflows must equal the initial cost of the project. a decrease in the project's initial cost will cause the project to have a negative NPV. any delay in receiving the projected cash inflows will cause the project to have a positive NPV. the project's PI must be also...