Question

A capital investment project requires an initial investment of $100 and generates positive cash flows, $50...

A capital investment project requires an initial investment of $100 and generates positive cash flows, $50 and $100, at the end of the first and second years, respectively. (There is no cash flow after the second year) The firm uses a hurdle rate of 15% for projects of similar risk.

Determine whether you should accept or reject the project based on NPV.

Determine whether you should accept or reject the project based on IRR.

Determine whether you should accept or reject the project based on MIRR.

Homework Answers

Answer #1

Calculation of NPV:

Year Expected cash flow Present value @15%
0 (100) (100)
1 50 43.4783
2 100 75.6144

NPV = 19.0927 i.e positive NPV Hence, project should be accepted.

Calculation of IRR of the project:

100=[50÷(1+r)]+[100÷(1+r)^2]

Following are steps of guessing r

Step:Compute excess cash flow per year=(50+100-100)/2=25

Step:Return on Initial Investment=(25/100)×100=25%

Step:Return on unrecovered investment balance=25×1.5=37.5

Step:Since cash flows are poor then reduce by 3% or 4%

At r = 32%

Right hand side = 39+58=97

Hence,IRR = 32%

Since approximate IRR is greater than hurdle rate this shows project should be accepted.

Calculation of MIRR:

(PV of return phase÷PV Of Initial Investment)this is under the root which is then multiplied by (1.15-1)

=square root of (119.0927/100)×(1.15-1)

=1.19092×.15

=.1786 or 17.86%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Grey company is analyzing a project that requires an initial investment of $600,000. The project's expected...
Grey company is analyzing a project that requires an initial investment of $600,000. The project's expected cash flows are: (Year 1) $350,000, (Year 2) -$125,000, (Year 3) $500,000 and (Year 4) $400,000. 1. Grey company's WACC is 10%, and the project has the same risk as the firm's average project. Calculate this project's modified internal rate of return (MIRR): _______%. 2. If Grey company's managers select projects based on the MIRR criterion, they should accept or reject this independent project....
Cute Camel Woodcraft Company is analyzing a project that requires an initial investment of $2,750,000. The...
Cute Camel Woodcraft Company is analyzing a project that requires an initial investment of $2,750,000. The project’s expected cash flows are: Year Cash Flow Year 1 $350,000 Year 2 –125,000 Year 3 400,000 Year 4 500,000 Cute Camel Woodcraft Company’s WACC is 9%, and the project has the same risk as the firm’s average project. Calculate this project’s modified internal rate of return (MIRR): 19.63% -16.48% 27.71% 25.40% If Cute Camel Woodcraft Company’s managers select projects based on the MIRR...
Light Sweet Petroleum, Inc., is trying to evaluate an exploration project with the following cash flows:...
Light Sweet Petroleum, Inc., is trying to evaluate an exploration project with the following cash flows: Year Cash Flow 0 -$39,000,000 1 63,000,000 2 -12,000,000 If the company requires a 12 percent return on its investments, should it accept this project? Yes, the IRR is below the 12% hurdle rate No, the IRR is above the 12% hurdle rate Cannot determine because there are multiple IRRs Yes, the NPV is positive No, the NPV is negative
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $450,000. The project’s expected cash flows are: Year Cash...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $400,000. The project’s expected cash flows are: Year...
Which of the following statements are correct? a. Consider a project that generates a negative cash...
Which of the following statements are correct? a. Consider a project that generates a negative cash flow in year 0 and a positive cash flow in year 1. The NPV rule will always lead to the same decision for this project as the IRR rule. b. Higher NPV projects have longer payback periods. c. Two projects with identical expected cash flows but different risk profiles have the same IRR. d. IRR is affected by the scale of the investment opportunity.
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at start of​ project: ​$13,000,000 Cash flow at end of year​ one: $2,080,000 Cash flow at end of years two through​ six: $2,600,000 each year Cash flow at end of years seven through​ nine: $2,496,000 each year Cash flow at end of year​ ten: $1,920,000 Risky Business wants to know the payback​ period, NPV,​ IRR, MIRR, and PI of this project. The appropriate discount rate...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at start of​ project: ​$11,700,000 Cash flow at end of year​ one: ​$2,106,000 Cash flow at end of years two through​ six: ​$2,340,000 each year Cash flow at end of years seven through​ nine: ​$2,527,200 each year Cash flow at end of year​ ten: ​$1,805,143 Risky Business wants to know the payback​ period, NPV,​ IRR, MIRR, and PI of this project. The appropriate discount rate...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,430 3 1 974 4 2 1,281 5 3 1,996 The required return is 8.5%. 1. What is the IRR for the project? 2. What is the NPV of the project? 3 .What should you do? Check all that apply: Reject the project based on its NPV Reject the project based on its IRR Accept the project based on its IRR...
If an investment project is described by the sequence of cash flows: Year Cash flow 0...
If an investment project is described by the sequence of cash flows: Year Cash flow 0 -300 1 -900 2 1100 3 500                 Calculate the MIRR, we will assume a finance rate of 8% and a reinvestment rate of 10%   [5] Find the IRR (using 7%, 10%, 11%) of an investment having initial cash outflow of $3,000. The cash inflows during the first, second, third and fourth years are expected to be $700, $800, $900 and $1,200 respectively            [5]...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT