Question

all the below is true regarding the payback period except Select one: a. does not consider...

all the below is true regarding the payback period except

Select one:
a. does not consider the time value of cash flow
b. does not consider the cash after the payback period
c. the best way to evaluate a long term with large capital projects
d. measures the performance of the management

Homework Answers

Answer #1

Payback period method is not the best method for evaluating long term with large capital project because these are only applicable for projects till they are returning back the initial money so they are not taking entire cash flow into the calculation perspective so they are not the best way to calculate long term projects.

Rest of the options are true regarding payback period because it will not consider time value and it will not consider cash after the payback period.

Correct answer will be option (C) the best way to evaluate a long-term with large capital product

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following statements concerning the payback period is NOT true     A.   The payback...
Which of the following statements concerning the payback period is NOT true     A.   The payback period is simple to calculate and understand.     B.   The payback period measures the time that a project will take to generate enough cash flows to cover the initial investment.     C.   The payback period ignores cash flows after the payback period has been achieved.     D.   The payback period takes account of the time value of money.
Which of the following statements about the "payback period" is true? The payback period fails to...
Which of the following statements about the "payback period" is true? The payback period fails to produce an objective decision to accept or reject an individual project. The payback period considers the time value of money. The payback period uses discounted cash-flow techniques. The payback period considers cash flows after the payback has been reached.
11. The NPV and payback period What information does the payback period provide? A project’s payback...
11. The NPV and payback period What information does the payback period provide? A project’s payback period (PB) indicates the number of years required for a project to recover its initial investment using its operating cash flows. As the theoretical soundness of the conventional (undiscounted) PB technique was criticized, the model was modified to incorporate the time value of money-adjusted operating cash flows to create the discounted payback method. While both payback models continue to reflect faulty ranking criteria, they...
Concerning payback, which of the following statements is true? a) Payback is no longer used since...
Concerning payback, which of the following statements is true? a) Payback is no longer used since it ignores the time value of money. b) Payback can only be used on simple projects since it cannot deal with cash flow. c) Payback period varies inversely with the benefit-cost ratio: the shorter the payback period, the higher the benefit-cost. d) Payback is only used for capital intensive projects.
Which one of the following statements is correct? A longer payback period is preferred over a...
Which one of the following statements is correct? A longer payback period is preferred over a shorter payback period. The payback rule states that you should accept a project if the payback period is less than one year. The payback period ignores the time value of money. The payback rule is biased in favor of long-term projects. The payback period considers the timing and amount of all of a project's cash flows.
7. The NPV and payback period What information does the payback period provide? Suppose Extensive Enterprises’s...
7. The NPV and payback period What information does the payback period provide? Suppose Extensive Enterprises’s CFO is evaluating a project with the following cash inflows. She does not know the project’s initial cost; however, she does know that the project’s regular payback period is 2.5 years. Year Cash Flow Year 1 $325,000 Year 2 $500,000 Year 3 $450,000 Year 4 $450,000 If the project’s weighted average cost of capital (WACC) is 8%, what is its NPV? $367,583 $312,446 $404,341...
ALL OF THE BELOW ARE TRUE ABOUT INTERNAL RATE OF RETURN EXCEPT Select one: a. ACCEPT...
ALL OF THE BELOW ARE TRUE ABOUT INTERNAL RATE OF RETURN EXCEPT Select one: a. ACCEPT THE PROJECT IF IRR IS LESS THAN THE DISCOUNT RATE b. NPV EQUAL ZERO c. ACCEPT THE PROJECT IF IRR IS HIGHER THAN THE DISCOUNT RATE d. IRR IS A WAY TO EVALUATE THE ACCEPTANCE OF A PROJECT Please Solve As soon as Solve quickly I get you two UPVOTE directly Thank's Abdul-Rahim Taysir
Which of the following statement is correct? Select one: a. Since the payback period method fails...
Which of the following statement is correct? Select one: a. Since the payback period method fails to look at the cash flows beyond the payback period, it can lead to poor business decisions. b. A firm should never accept the independent projects having NPVs greater than zero. c. The capital budgeting projects may be about the purchase of financial asset such as investing in stocks and bonds, futures, or buying and selling T-bills. d. The number of time periods it...
How does the use of payback period, net present value, and internal rate of return for...
How does the use of payback period, net present value, and internal rate of return for capital budgeting projects connect directly with a firm’s strategic goals? What factors in the political, business, and economic climate or environment have a direct correlation to capital budgeting projects? What potential short-term and long-term impact on capital budgeting projects might these factors have?
All of the following are true regarding benchmarking EXCEPT: that the purpose is to gather information...
All of the following are true regarding benchmarking EXCEPT: that the purpose is to gather information regarding the best practices of others. that buy-in by employees is critical. benchmarking can save time and money by avoiding the mistakes made by others. benchmarking initiatives generally result in quick changes to the work environment.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT