Question

Project X and Project Y are two mutually exclusive projects. Project X requires an initial outlay...

Project X and Project Y are two mutually exclusive projects. Project X requires an initial outlay of $38,000 and generates a net cash flow of $14,000 per year for six years. Project Y requires an initial outlay of $52,000, and will generate cash flows of $15,300 per year for eight years. Which project should be chosen and why? (Assume that the discount rate for both projects is 10 percent).
A.  Project X because Project X has a larger NPV than Project Y.
B.  Project Y because Project Y has a larger NPV than Project X.
C.  Project Y because Project Y has a larger Equivalent Annual Series than Project X.
D.  Project X because Project X has a larger Equivalent Annual Series than Project Y.
E.  Both projects X and Y because both projects have positive NPV.

Homework Answers

Answer #1

equivalent annual cash flow for X = (initial investment/PVAF )-annual cash inflow

(-38000/4.3552)+14000

5274.79794

equivalent annual cash flow for Y = (initial investment/PVAF )-annual cash inflow

(-52000/5.3349)+15300

5552.86322

NPV of Equivalent annual cash flow of X = equivalent annual cash flow*PVAF at 10% for 6 Years

5274.9195*4.3552

22973.3294

NPV of Equivalent annual cash flow of Y = equivalent annual cash flow*PVAF at 10% for 6 Years

5552.911*4.3552

24184.038

Answer is B

Project Y as it NPV of equivalent cash flow is more than Project X

PVAF at 10% for 6 Years

1-(1+r)^-n / r

1-(1.1)^-6 / .10

4.3552

PVAF at 10% for 8 Years

1-(1+r)^-n / r

1-(1.1)^-8 / .10

5.3349

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A firm is considering the two mutually exclusive investments projects. Project Alpha requires an initial outlay...
A firm is considering the two mutually exclusive investments projects. Project Alpha requires an initial outlay of $600 and will return $160 per year for the next seven years; Project Beta requires an initial outlay of $1,100 and will return $350 per year for the next five years. Assuming a 11% required return, calculate the NPV, Payback Period, and MIRR of each project. Please help by showing Excel calculations. Thanks!
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash...
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $32,500, and its expected cash flows would be $13,050 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Consider the following two mutually exclusive projects: Initial Net Cash Flow Per Year Outlay 1 2...
Consider the following two mutually exclusive projects: Initial Net Cash Flow Per Year Outlay 1 2 3 4 Project X $8,000 $4,400 $4,400 $4,400 $4,400 Project Y $8,000 $0 $15,000 Notice that Project X has a 4 year life span while Project Y has only a 2 year life span. A) Calculate the NPV, IRR, and EAA for each of these two projects, assuming a 10% discount rate. B) Use your calculations to clearly explain which project should be undertaken.
Two mutually exclusive projects have an initial cost of $60,000 each. Project A produces cash inflows...
Two mutually exclusive projects have an initial cost of $60,000 each. Project A produces cash inflows of $30,000, $37,000, and $20,000 for Years 1 through 3, respectively. Project B produces cash inflows of $80,000 in Year 2 only. The required rate of return is 10 percent for Project A and 11 percent for Project B. Which project(s) should be accepted and why? Project A, because it has the higher required rate of return. Project A, because it has the larger...
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has...
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has an initial outlay of $10,000, an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an initial outlay of $15,000, an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, and the projects have different lives. If the projects are repeatable, then: You should do both...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $12,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $50,000, and its expected cash flows would be $13,750 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Project S,...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $28,500, and its expected cash flows would be $13,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $12,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $45,000, and its expected cash flows would be $13,150 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Neither Project...
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment...
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment of $37,000 today and is expected to generate cash flows of $31,000 for the next 4 years. Project Beta requires an initial investment of $92,000 and is expected to generate cash flows of $36,400 for the next 8 years. The cost of capital is 10%. The projects can be repeated with no change in cash flows. What is the NPV of the project that...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT