Question

Calculate the payment and performance bond premium for a contract for a building project with an...

Calculate the payment and performance bond premium for a contract for a building project with an estimated cost of $12.5 million. Project duration is estimated at 18 months. If the project actual cost turns out to be $12.75m (same duration), what is the adjustment for the premium (how much extra should the contractor pay the surety)?

Homework Answers

Answer #1

Details Given:

Estimated cost of building project: $12.5 million

Actual Cost of building: $12.75 million

Estimated Duration of project completion: 18 months

Actual completion of project: 18 months

Working:

Particulars Amount
Estimated Cost (A) $12.50
Actual Cost (B) $12.75
Balance (C = B - A) $0.25

Since the period of estimation of project completion and actual completion of project is same i.e. 18 months, the contractor has to pay $0.25 million extra.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A construction company enters into a contract with a customer to supply a new building. Control...
A construction company enters into a contract with a customer to supply a new building. Control over the completed building will pass to the customer in two years (the contractor’s performance obligation will be satisfied at a point in time). The contract contains two payment options. Either the customer can pay $ 5 million in two years when it obtains control of the building, or the customer can pay $ 4 million on inception of the contract. The customer decides...
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building....
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:      2020             2021 Actual costs incurred $ 120,000      $ 204,000 Estimated costs to complete 200,000               -0- Progress billings 112,000        248,000 Collections 110,000        250,000 Instructions (show all supporting calculations) Calculate how much...
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent...
Data for a project is given below: Activity Duration (months) Precedence Budget or Plnd. Cost Percent Completed A 3.00 - 15000 1.00 B 1.00 A 5000 0.00 C 2.00 A 10000 1.00 D 3.00 A 21000 0.50 E 2.00 B,C 32000 0.00 F 1.00 C 5000 0.00 G 1.00 C 5500 0.00 The project started on June 1st. The project has a planned duration of 7 months. Data below are planned cost and actual cost (spent) from June to November:...
Hector is a building contractor and entered into a contract on February 1, 2018 to build...
Hector is a building contractor and entered into a contract on February 1, 2018 to build a house for Lois for $350,000 with a completion date of July 1, 2018. Payments are to be made to Hector by Lois of $50,000 on the signing of the contract, $150,000 on April 1, provided the house is partially completed as defined in the contract, and $150,000 on July 1, 2018, when the house is fully completed. Lois is very clear that the...
You are the risk manager for your company. In three months it will receive a payment...
You are the risk manager for your company. In three months it will receive a payment of A$50 million. The three month forward rate is AUDUSD 0.9015. a. In your opinion, should you hedge Australian $ revenue (that is, lock in your US dollar inflow today using the forward price)? b. Suppose you do decide to hedge the exposure. What is your hedged USD revenue? c. Suppose the actual exchange rate turns out to be AUDUSD 0.9259. Did you have...
Multiple Choice: Please select the correct answer 1. Progress payments are generally issued A - whenever...
Multiple Choice: Please select the correct answer 1. Progress payments are generally issued A - whenever the contractor submits the bill B - whenever the subcontractor submits the bill C - every 45 days D - every 30 days 2. In order to pay the progress payment, who must certify the amount? A - the contractor B - purchasing agent C - design professional D - the owner 3. Retainage is generally withheld from each process payment. The process of...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT