Question

An increase in the discount rate used in DCF analysis of a project penalizes the cash...

An increase in the discount rate used in DCF analysis of a project penalizes the cash flows from its later years more than those from its early years.

True

False

Homework Answers

Answer #1

Hello Sir/ Mam

YOUR REQUIRED ANSWER IS TRUE.

We discount the cashflows as per the receipt year. Earlier cashflows are discounted less and later cashflows are discounted more. The more later the cashflow, the more discounting is required. Hence, it is justified that increase in discount rate used in DCF analysis of a project penalizes cashflows from its later years more than those from its early years.

I hope this solves your doubt.

Do give a thumbs up if you find this helpful.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The discount rate that is used for calculating the present values of a project's cash flows...
The discount rate that is used for calculating the present values of a project's cash flows is the rate of return on other investments, which have lower risk than that of the project. True False Diversification helps the investor to significantly reduce the standard deviation of their investment as they create a portfolio by allocating their investment to different securities. True False Variance of an investment's returns shows the exact percentage of the investment's risk. True False
1. Project A, which costs of $1,000 to purchase, will generate net cash inflows equal to...
1. Project A, which costs of $1,000 to purchase, will generate net cash inflows equal to $500 at the end of each of the next three years. The project's required rate of return is 10 percent. What are the project's internal rate of return (IRR) and modified internal rate of return (MIRR)? 23.4%; 38.2% 14.5%; 12.6% 16.7%; 18.3% 23.4%; 16.7% 23.4%; 18.3% 2. The internal rate of return (IRR) of a project that generates its largest cash flows in the...
Based on the dividend discount model, an increase in discount rate will lower the current value...
Based on the dividend discount model, an increase in discount rate will lower the current value of a stock. True or False Under the dividend discount model, for the first few years, a company can have a growth rate that is higher than the discount rate. True or False 7.0.1
A project has an NPV of £12,632 when a discount rate of 12% is used and...
A project has an NPV of £12,632 when a discount rate of 12% is used and the same project has an NPV of (£6,935) when a discount rate of 24% is used. The approximate internal rate of return of the project is: Select one: a. 18.5% b. 15.16% c. 20.5% d. 19.75% An investment project costs $10,500 and will generate $4,000 in annual cash flows for five years. What is the exact internal rate of return (IRR)? Select one: a....
Using Internal Rate of Return (IRR) for analysis can be flawed because a. the discount rate...
Using Internal Rate of Return (IRR) for analysis can be flawed because a. the discount rate can be overstated b. project cash flows are expected to be reinvested at the internal rate of return c. the project's cash flows can be back loaded d interest rates can change over time for extended projects e it is generally easier to understand a project's Net Present Value rather than its Internal Rate of Return
6. You have determined the profitability of a planned project by finding the present value of...
6. You have determined the profitability of a planned project by finding the present value of all the cash flows from that project. Which of the following would cause the project to look more appealing in terms of the present value of those cash flows? A. The discount rate decreases. B. The cash flows are extended over a longer period of time, but the total amount of the cash flows remains the same. C. The discount rate increases. D. Answers...
Rosita's is considering a project with a discount rate of 9 percent. If the firm starts...
Rosita's is considering a project with a discount rate of 9 percent. If the firm starts the project today, it will incur an initial cost of $32,260 and will receive cash inflows of $18,320 a year for 4 years. If the firm waits 1 year to start the project, the initial cost will decrease to $30,500, the cash flows will increase to $18,640 a year for 4 years, and the discount rate will decrease to 8.5 percent. What is the...
You are considering a project with a discount rate of 10%. If you start the project...
You are considering a project with a discount rate of 10%. If you start the project today, you will incur an initial cost of $500 and will receive cash inflows of $350 a year for three years. If you wait one year to start the project, the initial cost will rise to $515 and the cash flows will increase to $365 a year for three years. What is the value of the option to wait (the difference in NPV today...
True or false. In DCF valuation, a company can increase its equity value by borrowing more...
True or false. In DCF valuation, a company can increase its equity value by borrowing more money provided that the after-tax cost of debt exceeds the return on capital. (Assume all other inputs are fixed.
An investment project has annual cash inflows of $5,400, $6,000, $7,300, and $8,600, and a discount...
An investment project has annual cash inflows of $5,400, $6,000, $7,300, and $8,600, and a discount rate of 10 percent. What is the discounted payback period for these cash flows if the initial cost is $9,000? options: 2.02 years 2.51 years 1.66 years 1.83 years 1.95 years A project that provides annual cash flows of $16,000 for 9 years costs $85,824 today. Assuming a discount rate of 13%, What is the NPV of this project? options: -3,850.33 1,872.49 2,825.92 4,291.68)...