Question

Calculate and choose project/s assuming that these two projects are (1) mutually exclusive OR (2) independent....

  1. Calculate and choose project/s assuming that these two projects are

(1) mutually exclusive OR

(2) independent.

NPV (WACC 6%)

CFs Year

A

B

0

-2050

-4300

1

750

1500

2

760

1518

3

770

1536

4

780

1554

Homework Answers

Answer #1

Since both projects are mutually exclusive and independent, we can choose both projects as they have net present value greater than zero.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ASaark Telecom is considering Projects S and L, whose cash flows are shown below. These projects...
ASaark Telecom is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value...
The company has to choose between to mutually exclusive projects, Project A and Project B. Which...
The company has to choose between to mutually exclusive projects, Project A and Project B. Which project (s) should the company implement if they have a 10% required rate of return? Year Project A Project B 0 $-50,000 $-10,000 1 $20,000 $5,000 2 $20,000 $5,000 3 $10,000 $2,000 4 $10,000 $2,000 5 $5000 $1500 Question 8 options: Only A Only B A & B Neither A nor B
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $874.66 $260 $5 $10 Project L -$1,000 $5 $240 $380 $797.82 The company's WACC is 10.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. A firm is considering two mutually exclusive projects, X and...
Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally...
Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the maximum possible NPV? WACC=8.75% Year 0 Year 1...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $868.18 $250 $10 $15 Project L -$1,000 $0 $260 $400 $827.46 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $896.74 $240 $10 $10 Project L -$1,000 $0 $260 $380 $840.52 The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $878.14 $250 $10 $15 Project L -$1,000 $0 $260 $400 $767.27 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %?
William Industries is attempting to choose the better of two mutually exclusive projects for expanding the...
William Industries is attempting to choose the better of two mutually exclusive projects for expanding the firm’s production capacity. The relevant cash flows for the projects are shown in the following table. The firm’s cost of capital is 15%. PROJECT B PROJECT C YEAR Cash Flow Cash Flow 0 350000 50000 1 45000 24000 2 65000 22000 3 65000 19500 4 440000 14600 a) Calculate the period back of each project, assess its acceptability, and indicate which project is best,...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $865.46 $260 $10 $15 Project L -$1,000 $10 $250 $400 $765.87 The company's WACC is 10.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $876.05 $260 $15 $5 Project L -$1,000 $10 $260 $380 $771.23 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.