Question

Suppose William Inc. uses a WACC of 9% for below-average risk projects, 11% for average-risk projects,...

Suppose William Inc. uses a WACC of 9% for below-average risk projects, 11% for average-risk projects, and 13% for above-average risk projects. Which of the following independent projects should William accept, assuming that the company uses the NPV method when choosing projects?

Project A, which has average risk and an IRR = 12%.

Project B, which has below-average risk and an IRR = 9.5%.

Project C, which has above-average risk and an IRR = 13.5%.

Without information about the projects' NPVs we cannot determine which one or ones should be accepted.

All of these projects should be accepted as they will produce a positive NPV.

Homework Answers

Answer #1

Correct answer: All of these projects should be accepted as they will produce a positive NPV.

A project would have positive net present value (NPV) when Internal rate of return (IRR) is greater than cost of capital of projet.

Project-A

WACC = 11%

IRR = 12%

IRR > WACC, Thus, NPV of Project A would be positive.

Project-B

WACC = 9%

IRR = 9.5%

IRR > WACC, Thus, NPV of Project B would be positive.

Project-C

WACC = 13%

IRR = 13.5%

IRR > WACC, Thus, NPV of Project C would be positive.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Puckett Inc. risk-adjusts its WACC to account for project risk. It uses a risk-adjusted project cost...
Puckett Inc. risk-adjusts its WACC to account for project risk. It uses a risk-adjusted project cost of capital of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects. Which of the following independent projects should Puckett accept, assuming that the company uses the NPV method when choosing projects? a. Project C, which has above-average risk and an IRR = 11%. b. Without information about the projects' NPVs we cannot determine which project(s) should be...
2) LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk...
2) LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%. Which of the following projects (A, B, and C) should the company accept? a) Project B, which of the below-average risk and had a return of 8.5% b) Project A, which is of average risk and has a return of 9% c) Project C, which is of above-average...
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of...
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of return of 8.25%. You have gathered the following data. Which of the project(s) should be accepted? IRR NPV Project A 6.40% $ 22.6 million Project B 8.50% $ 16.1 million A) Accept neither project, as both have a required return that is above the IRR. B) Accept project B with the higher IRR. C) Accept project A with the higher NPV. D) Accept both...
Please show me how to calculation with these question. A company estimates that an average-risk project...
Please show me how to calculation with these question. A company estimates that an average-risk project has a WACC of 12%, a below-average risk project has a WACC of 10%, and an above-average risk project has a WACC of 14%. Which of the following independent projects should the company accept? Project Y has below-average risk and an internal rate of return of 9%.   Project X has average risk and an internal rate of return of 11%.   Project Z has above-average...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$9,000 $3,000 $3,000 $3,000 $3,000 $3,000 Project N -$27,000 $8,400 $8,400 $8,400 $8,400 $8,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
If a firm uses its weighted average cost of capital (WACC) to evaluate all capital budgeting...
If a firm uses its weighted average cost of capital (WACC) to evaluate all capital budgeting projects, which of the following could occur? a. Projects with little or no risk might be rejected when they actually should be accepted. b. Projects with significant risks might be accepted when the actually should be rejected. c. Projects with average risk will always be rejected when they actually should be rejected. d. All of the above could occur. e. None of the above...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$27,000 $9,000 $9,000 $9,000 $9,000 $9,000 Project N -$81,000 $25,200 $25,200 $25,200 $25,200 $25,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter payback will not cause value to be lost. WACC: 10.25% 0    1 2 3 4...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both projects is 10%. The first project has an IRR of 22% and an NPV of $22,432. The second project has an IRR of 12% and an NPV of $24,456. Which project should you select? accept both projects since both are acceptable. pick the project with the shorter payback period. choose the project with the higher NPV. unable to determine due to insufficient information. choose...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT