Question

Cullumber Crafts Corp. management is evaluating two independent capital projects that will each cost the company...

Cullumber Crafts Corp. management is evaluating two independent capital projects that will each cost the company $290,000. The two projects will provide the following cash flows: Year Project A Project B 1 $84,750 $66,000 2 103,450 99,000 3 24,235 137,250 4 129,655 98,110 Collapse question part (a1) What is the payback period of both projects? (Round answers to 2 decimal places, e.g. 15.25.)

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,304,168 -$1,325,262 1 264,000 379,000 2 365,000 379,000 3 445,000 379,000 4 539,000 379,000 5 739,000 379,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to...
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,292,224 -$1,321,796 1 238,000 384,000 2 329,000 384,000 3 430,000 384,000 4 504,000 384,000 5 800,000 384,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to...
Management of Crane Measures, Inc., is evaluating two independent projects. The company uses a 12.62 percent...
Management of Crane Measures, Inc., is evaluating two independent projects. The company uses a 12.62 percent discount rate for such projects. The costs and cash flows for the projects are shown in the following table. Year Project 1 Project 2 0 - $8,066,549 - $11,655,500 1 3,003,590 2,165,830 2 1,608,490 3,783,590 3 1,465,800 2,820,680 4 1,061,800 4,040,500 5 1,153,880 4,449,580 6 1,708,040 7 1,266,990 a. What are the IRRs for the projects? (Round final answer to 2 decimal places, e.g....
Timeline Manufacturing Co. is evaluating two projects. The company uses payback criteria of three years or...
Timeline Manufacturing Co. is evaluating two projects. The company uses payback criteria of three years or less. Project A has a cost of $845,140, and project B’s cost is $1,190,400. Cash flows from both projects are given in the following table. Year Project A Project B 1 $86,212 $586,212 2 313,562 413,277 3 427,594 231,199 4 285,552 What are their discounted payback periods? (Round answers to 2 decimal places, e.g. 15.25. If discounted payback period exceeds life of the project,...
A firm with a cost of capital of 10% is evaluating two independent projects utilizing the...
A firm with a cost of capital of 10% is evaluating two independent projects utilizing the internal rate of return technique. Project X has an initial investment of $70,000 and cash inflows at the end of each of the next five years of $25,000. Project Z has an initial investment of $120,000 and cash inflows at the end of each of the next four years of $35,000. The firm should ________. accept Project X and reject project Z accept both...
Cullumber Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive,...
Cullumber Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 9 percent discount rate for their production systems. Year System 1 System 2 0 -$15,100 -$42,300 1 15,100 30,800 2 15,100 30,800 3 15,100 30,800 What are the payback periods for production systems 1 and 2? (Round answers to 2 decimal places,...
A company is evaluating two independent projects for capital investment purposes. If the company has only...
A company is evaluating two independent projects for capital investment purposes. If the company has only $85 million to invest, and its required return is 10 percent by how much the company’s value will increase? All values are in millions. Project 1 Project 2 0 -50 -50 1 5 0 2 15 0 3 30 0 4 30 90
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate is 10%. The first project (A) will cost $25,000 initially. The project will then return cash flows of $8,000 for 4 years. The second project (B) will cost $40,000 initially. The project will then return cash flows of $15,000 for the next 2 years and $10,000 for 2 years after that. The third project (C) will cost $30,000 initially. The project will then return...
A company is evaluating two independent projects for capital investment purposes. If the company has only...
A company is evaluating two independent projects for capital investment purposes. If the company has only $85 million to invest, and its required return is 10 percent by how much the company’s value will increase? All values are in millions. Project 1 Project 2 0 -50 -50 1 5 0 2 15 0 3 30 0 4 30 90 $30.53 $11.47 $9.97 $21.44 $19.06
As the director of capital budgeting for Denver Corp., you are evaluating two mutually exclusive projects...
As the director of capital budgeting for Denver Corp., you are evaluating two mutually exclusive projects with the following net cash flows:                               Project X               Project Z               Year       Cash Flow              Cash Flow               0              -$100,000             -$100,000               1                   50,000                  10,000               2                   40,000                  30,000               3                   30,000                  40,000               4                   10,000                  60,000 If Denver’s cost of capital is 15 percent, which project would you choose? Neither project. Project X, since it has the higher IRR. Project Z, since it has the higher NPV. Project X, since it has the higher NPV. Project Z, since it has the higher IRR....