Question

The Basics of Capital Budgeting: NPV Profile A project's NPV profile graph intersects the Y-axis at...

The Basics of Capital Budgeting: NPV Profile

A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's -Select-paybackMIRRIRRCorrect 1 of Item 1 (where NPV = 0). The Y-axis intersection point represents the project's undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the -Select-IRRpaybackMIRRCorrect 2 of Item 1 of the differences in the projects' cash flows (Project Delta). A -Select-flatsteepCorrect 3 of Item 1 NPV profile indicates that increases in the cost of capital lead to large declines in NPV. If a project has most of its cash flows coming in later years, its NPV will -Select-declineriseCorrect 4 of Item 1 sharply if the cost of capital increases; but a project whose cash flows come earlier will not be severely penalized by high capital costs. The significance of the crossover rate is that at any cost of capital -Select-lessgreaterCorrect 5 of Item 1 than the crossover rate, the NPV and IRR methods will provide the same conclusion for evaluating mutually exclusive projects. However, at any cost of capital -Select-lessgreaterCorrect 6 of Item 1 than the crossover rate, the NPV and IRR methods' conclusions will conflict. In that situation, the -Select-IRRNPVMIRRpaybackCorrect 7 of Item 1 method will always provide the correct project acceptance result.

Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%.

0 1 2 3 4
Project A -1,050 705 360 200 310
Project B -1,050 320 305 400 655

What is Project Delta's IRR? Do not round intermediate calculations. Round your answer to two decimal places.

%

What is the significance of this IRR?

It is the -Select-equity returncrossover rateinterest yieldCorrect 1 of Item 2, after this point when mutually exclusive projects are considered there is no conflict in project acceptance between the NPV and IRR approaches.

Review the graphs below. Select the graph that correctly represents the correct NPV profile for Projects A and B by using the following drop down menu.

-Select-ABCDCorrect 2 of Item 2
   

Homework Answers

Answer #1

1.
A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's IRR (where NPV = 0). The Y-axis intersection point represents the project's undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the IRR of the differences in the projects' cash flows (Project Delta). A steep NPV profile indicates that increases in the cost of capital lead to large declines in NPV. If a project has most of its cash flows coming in later years, its NPV will decline sharply if the cost of capital increases; but a project whose cash flows come earlier will not be severely penalized by high capital costs. The significance of the crossover rate is that at any cost of capital higher than the crossover rate, the NPV and IRR methods will provide the same conclusion for evaluating mutually exclusive projects. However, at any cost of capital less than the crossover rate, the NPV and IRR methods' conclusions will conflict. In that situation, the NPV method will always provide the correct project acceptance result.

2.
=IRR({0;385;55;-200;-345})
=8.93%

3.
crossover rate

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen....
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 11%. 0 1 2 3 4 Project A...
Capital Budgeting Decision Criteria: NPV NPV The net present value (NPV) method estimates how much a...
Capital Budgeting Decision Criteria: NPV NPV The net present value (NPV) method estimates how much a potential project will contribute to -Select-business ethicsshareholders' wealthemployee benefitsCorrect 1 of Item 1, and it is the best selection criterion. The -Select-smallerlargerCorrect 2 of Item 1 the NPV, the more value the project adds; and added value means a -Select-higherlowerCorrect 3 of Item 1 stock price. In equation form, the NPV is defined as: CFt is the expected cash flow in Period t, r...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 9%. 0 1 2 3 4 Project A...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
I cannot figure this one out! NPV profile of two mutually exclusive projects. Moulton Industries has...
I cannot figure this one out! NPV profile of two mutually exclusive projects. Moulton Industries has two potential projects for the coming? year, Project? B-12 and Project? F-4. The two projects are mutually exclusive. The cash flows are listed in the following table. Draw the NPV profile of each? project, and determine their crossover rate. If the appropriate hurdle rate is? 8% for both?projects, which project does Moulton Industries? choose? ??Cash Flow Project? B-12 Project? F-4 ??Year 0 ??$4,210,000 ??$3,780,000...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$27,000 $9,000 $9,000 $9,000 $9,000 $9,000 Project N -$81,000 $25,200 $25,200 $25,200 $25,200 $25,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
You are a financial analyst for Hittle Company. The director of capital budgeting has asked you...
You are a financial analyst for Hittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each project is 10 percent. The payback cutoff period is 3 years. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project X 0 ($10,000) 1 6,500 2 3,000 3 3,000 4 1,000 Project Y ($10,000)...
Capital Budgeting: 1. T/F If the NPV<0, the WACC > the IRR 2.T/F Salvage value is...
Capital Budgeting: 1. T/F If the NPV<0, the WACC > the IRR 2.T/F Salvage value is added back in to the last years projects cash flows 3. T/F NPV is considered to be the superior method for choosing capital budget projects 4. T/F If projects are mutually exclusive, if one has a higher IRR choose that project over the NPV decision. Cost of Capital 5. T/F external equity (new stock issuance) is less expensive since it will have a flotation...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT