Question

Suppose you are a financial manager and you have the following investment opportunities: Project Investment (in...

Suppose you are a financial manager and you have the following investment opportunities:

Project

Investment (in $1,000)

NPV (in $1,000)

1

500

100

2

200

-4

3

125

-7

4

50

50

5

250

60

Which of the following projects should you pursue if you have only $700,000 allocated for capital expenditures? How much does the budget limit cost the company in terms of forgone NPV? The opportunity cost of capital for each project is 15%.

Homework Answers

Answer #1

Out of the 5 projects that can be pursued, only project 1 , 4 and 5 have positive net present value. Project 2 and 3 have negative net present value and hence they will not be pursued.

Project 1 has an investment of $ 500,000 and if investment is made in project 1, then we are left with only $ 200,000 to make investments into other projects. We cannot make investment into project 5 because it requires an investment of $ 250,000 . Hence the only investment we can make other than project 1 is project 4.

The total NPV from selecting project 1 and project 4 equals $ 150,000.

Due to limited budget, the cost to the company in terms of foregone NPV equals $ 60,000.

If the firm did not have limited budget, it could have pursued project 5 as well which would have resulted in total NPV of $ 210,000.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company is considering the following investment opportunities: Project A Initial cost = $5,500,000 Expected life...
A company is considering the following investment opportunities: Project A Initial cost = $5,500,000 Expected life = 10 yrs NPV = $340,000 IRR = 20% Project B Initial cost = $3,000,000 Expected life = 10 yrs NPV = $300,000 IRR = 30% Project C Initial cost = $2,000,000 Expected life = 10 yrs NPV = $200,000 IRR = 40% If the company has a WACC of 15% and the company is using capital rationing with a fixed capital budget of...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has a project beta of 2.0 and you have estimated that the project’s NPV using a cost of capital of 20% equals zero. Project 2 has a project beta of 1.5 and its NPV using a cost of capital of 10% equals zero. Project 3 has a project beta of 1.0 and its NPV equals zero using a cost of capital of 6%. None of...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has...
Assume CAPM holds and you have the following information regarding three investment opportunities: Project 1 has a project beta of 2.0 and you have estimated that the project’s NPV using a cost of capital of 20% equals zero. Project 2 has a project beta of 1.5 and its NPV using a cost of capital of 10% equals zero. Lastly, project 3 has a project beta of 1.0 and its NPV equals zero using a cost of capital of 6%. None...
B Pharmaceuticals has $750,000 allocated for capital expenditures. Which of the following projects should the company...
B Pharmaceuticals has $750,000 allocated for capital expenditures. Which of the following projects should the company accept to stay within the $750,000 budget? How much does the budget limit cost the company in terms of its market value? The opportunity cost of capital for each project is 11 percent. Project Investments ($ thousands) NPV ($ thousands) IRR % 1 300 66 17.2 2 200 -4 10.7 3 100 14 12.1 4 350 73 18 5 400 48 13.5
Suppose you are a manager and you have three potential capital investment projects from which to...
Suppose you are a manager and you have three potential capital investment projects from which to choose. You are on a limited budget so you can only choose one of the three potential projects. Describe at least three methods you can use to select the one project in which to invest.
You are deciding between two mutually exclusive investment opportunities. Both require the same initial investment of...
You are deciding between two mutually exclusive investment opportunities. Both require the same initial investment of $11.0 million. Investment A will generate $2.40 million per year (starting at the end of the first year) in perpetuity. Investment B will generate $1.70 million at the end of the first year, and its revenues will grow at 3.2% per year for every year after that. Which investment has the higher IRR ? Which investment has the higher NPV when the cost of...
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (350 ) $ (350 ) 1 180 250 2 180 250 3 180 250 4 180 a. Calculate the NPV for both projects if the opportunity cost of capital is 16%. (Do not round intermediate calculations. Round your answers to 2 decimal places.)
A company has the following mutually exclusive investment alternatives: Year          Project A         Project B 0       &
A company has the following mutually exclusive investment alternatives: Year          Project A         Project B 0                -$1,000            -$1,000 1                      800                1,300 2                      800                   600 3                      800                   500 If the cost of capital is 10%, which investment(s) should the company select? Project A with a NPV of $989.48 Project B with a NPV of $989.48 Both project A and project B Project B with a NPV of $1,053.34 Project A with a NPV of $1,075.96
Hawkeye Corp has two investment opportunities with the following cash flows and IRRs. Hawkeye’s required return...
Hawkeye Corp has two investment opportunities with the following cash flows and IRRs. Hawkeye’s required return on each project is 9%. The projects are not mutually exclusive, so Hawkeye could invest in both projects if it wants to. Which projects should Hawkeye invest in using NPV? Year 0 Year 1 Year2 Project A -$6,000 $1,500 $6,500 Project B $2,000 -$1,000 -$1,500 Group of answer choices Both projects A and B Only project B Only project A Neither project Mass Company...
A company has three independent investment opportunities. Each investment costs $1,000, and the firm's cost of...
A company has three independent investment opportunities. Each investment costs $1,000, and the firm's cost of capital is 10%. The cash inflow of each investment is as follows:                  cash inflow   A          B          C              year                 1               $300       500       100                 2                 300       400       200                 3                 300       200       400                 4                 300       100       500 If the company uses net present value method to evaluate its investments, which investment(s) should the firm make? investment...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT