Question

You are considering two mutually exclusive projects. Project A has an IRR of 10% Project B...

You are considering two mutually exclusive projects.

Project A has an IRR of 10%

Project B has an IRR of 8%

The crossover rate is 6%

Which project will have the greatest NPV if the Required Return is 4%

Group of answer choices

Project A and B would have the same NPV

There is not enough information to answer this question.

Project B

Project A

Homework Answers

Answer #1

The use of IRR, as a criterion to accept capital investment decision involves a comparison of IRR with the required rate of return known as cut off rate. The project should the accepted if IRR is greater than cut-off rate. If IRR is equal to cut off rate the firm is indifferent. If IRR less than cut off rate the project is rejected. Thus,

  If IRR ≥ Cut-off Rate or WACC - Accept the Proposal

  If IRR ≤ Cut-off Rate or WACC - Reject the Proposal

According to the question, Project A's IRR (10%) is greater than cross-over rate (6%) i.e. 4% (10%-6%) more than cross-over rate & Project B's IRR (8%) is also greater than cross-over rate (6%) i.e 2% (8%-6%) which is marginally more than cross-over rate.Therefore, Project A's NPV will be higher as compare with Project B so that company should opt Project A.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Projects A and B are mutually exclusive and have the following cash flows: Year Project A...
Projects A and B are mutually exclusive and have the following cash flows: Year Project A Project B 0 -$82,000 -$82,000 1 34,000 0 2 34,000 0 3 34,000 108,000 1. What is the crossover rate? 2. Do we have a conflict in ranking between the NPV and IRR methods if the required rate of return is 8%? 3. Which project should be accepted if the required rate of return is 5%? 4. Which project should be accepted if the...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$40,000 −$40,000 1 21,500 13,730 2 13,500 11,500 3 13,500 25,700
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$21,000 −$21,000 1 7,000 15,040 2 7,000 5,000 3 15,000 7,060 16.70%; A 12.59%; B 12.59%; A 15.61%; B 15.61%; A
You are considering the following two mutually exclusive projects with the following cash flows:                           &nbsp
You are considering the following two mutually exclusive projects with the following cash flows:                                                                                  Project A                                  Project B                                                             Year    Cash Flow                   Year    Cash Flow                                                             0          -$75,000                         0       -$70,000                                                             1          $19,000                         1       $10,000                                                             2          $48,000                         2       $16,000                                                             3          $12,000                         3       $72,000                        Required rate of return                     10 %                                        13 %                             Calculate the NPV, IRR,...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$21,000 −$21,000 1 7,000 15,040 2 7,000 5,000 3 15,000 7,060 Multiple Choice 12.59%; B 15.61%; A 15.61%; B 12.59%; A 16.70%; A
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both projects is 10%. The first project has an IRR of 22% and an NPV of $22,432. The second project has an IRR of 12% and an NPV of $24,456. Which project should you select? accept both projects since both are acceptable. pick the project with the shorter payback period. choose the project with the higher NPV. unable to determine due to insufficient information. choose...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,600 -8,400 1 1,325 1,325 2 2,148 2,148 3 4,193 8,192 The required return for both projects is 8%. Part 1 : What is the IRR for project A? 3+ Decimals Part 2 What is the IRR for project B? 3+ Decimals Part 3 Which project seems better according to the IRR method? Project A or Project B Part 4 What...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$27,000 −$27,000 1 10,000 18,100 2 10,000 8,000 3 18,000 10,120 Multiple Choice a.) 18.64%; A b.) 11.75%; B c.) 11.75%; A d.) 17.19%; B e.) 17.19%; A
Kilroy, Inc. is considering two mutually exclusive projects. The cash flows of the projects are as...
Kilroy, Inc. is considering two mutually exclusive projects. The cash flows of the projects are as follows: Year Project A Project B 0 -$2,000,000 -$2,000,000 1 500,000 2 500,000 3 500,000 4 500,000 5 500,000 6 500,000 7 500,000 5,650,000 a. Compute the NPV and IRR for the above two projects, assuming a 13% required rate of return. NPV for project A= b. Discuss any potential conflict in evaluating these candidate projects. c. What decision should be made regarding these...
You are considering two mutually exclusive projects with the following cash flows. Which project would you...
You are considering two mutually exclusive projects with the following cash flows. Which project would you choose? (The following is the only information you have. Don’t ask for more because I don’t have any more information?) Hint: Find the “crossover rate” to answer. PLEASE SHOW & EXPLAIN ALL WORK Year Project A Project B 0 -240,000 -198,000 1 0 110,800 2 0 82,500 3 325,000 45,000
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT