Question

2. A project has the following cash flows             C0                    C1    &n

2. A project has the following cash flows

            C0                    C1                    C2                    C3       

                               ($1000)             $300                $400                $600

What is the project’s payback period?

Year

0

1

2

3

Cash Flow

($1000)

$300

$400

$600

Cumulative

($1000)

($700)

($300)

300

a. Calculate the projects NPV at 10%.

b. Calculate the project’s PI at 10%.

c. Calculate an IRR for the project in question 2

How would you answer a,b, and c in excel? I am getting 2,054.09 for NPV and not sure if that is correct.

Homework Answers

Answer #1


Year

Cash flows = CF

Df = 1/(1+10%)^Year

Present Value = CF x Df

0

-1,000.00

1.000000

-1,000.00

1

300.00

0.909091

272.7273

2

400.00

0.826446

330.5785

3

600.00

0.751315

450.7889

Total PV = NPV =

54.09

NPV = 54.09

PI or BC = PV of Cash Inflows / Investment = (272.7273+330.5785+450.7889)/1000 = 1.05

------

NPV of discrete cash flows has to be done manually there is no excel formula, we can used excel to make tables and used formula at each node.

(I think you are adding initial investment to total PV of inflows = (272.7273+330.5785+450.7889) + 1000 = 2054.09 which is not correct… Do this = (272.7273+330.5785+450.7889) - 1000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Suppose the cash flows for project are C0 = -2000; C1 = 500; C2 = 1000;...
Suppose the cash flows for project are C0 = -2000; C1 = 500; C2 = 1000; C3 = 4000, C4= 1000, C5= 500. The discounted payback period is ____________________ and profitability index is ___________________ at a discount rate of 10 percent.
A project has the following forecasted cash flows: Cash Flows Thousands of dollars C0 C1 C2...
A project has the following forecasted cash flows: Cash Flows Thousands of dollars C0 C1 C2 C3 -100 40 60 50 The investor expected rate of return is 10%. The cost of capital is 12%. Required: 1.What will you choose to be the discount rate? Why? 2.Please calculate the payback period (PP) and return on investment (ROI). 3.Please calculate NPV,PVI and IRR.. 4.Make decision based on the above calculation and explain the reasons. 5.David said that the profit is the...
2. A company is considering a project that has the following cash flows: C0 = -3,000,...
2. A company is considering a project that has the following cash flows: C0 = -3,000, C1 = +900, C2 = +500, C3 = +1,100, and C4 = +1,900, with a risk-adjusted discount rate of 8%. A) Calculate the Net Present Value (NPV), Internal Rate of Return (IRR), Modified Internal Rate of Return (MIRR), and Profitability Index (PI) of this project. B) If you were the manager of the firm, will you accept or reject the project based on the...
Here are the the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3...
Here are the the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A -21,200 9,328 9,328 9,328 B -21,200 0 0 28,620 what is the IRR of each project? (round answer to 2 decimal places)
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 22,200 +$ 9,768 +$ 9,768 +$ 9,768 B − 22,200 0 0 + 29,970 What is the IRR of each project? (Round your answers to 2 decimal places.)
The following cash flows are given for a project C0 = -9000 C1= +9000 C2= +18000...
The following cash flows are given for a project C0 = -9000 C1= +9000 C2= +18000 The NPV of the project at a discount rate of 50% is: A.) 18,000 B.) 5,000 C.) 11,000 D.) zero or E.) none of these The IRR for this project is: A.) 10% B.) 25% C.) 50% D.) 100% or E.) none of these The payback period for this project is: A.) zero years B.) one year C.) two years D.) three years or...
Consider projects A and B: Cash Flows (dollars) Projects A B C0 450,000 320,000 C1 310,000...
Consider projects A and B: Cash Flows (dollars) Projects A B C0 450,000 320,000 C1 310,000 80,000 C2 120,000 100,000 C3 85,000 250,000 What is the NPV at 10% required rate? Which is the best Project?
Consider projects A and B: Cash Flows (dollars) Projects A B C0 450,000 320,000 C1 310,000...
Consider projects A and B: Cash Flows (dollars) Projects A B C0 450,000 320,000 C1 310,000 80,000 C2 120,000 100,000 C3 85,000 250,000 What is the NPV at 10% required rate? Which is the best Project?
A project has the following cash flows. C0 C1 C2 C3 ($770) $290 $530 $236 Calculate...
A project has the following cash flows. C0 C1 C2 C3 ($770) $290 $530 $236 Calculate an IRR for the project using an iterative technique. (Hint: Start by guessing 17%.) Do not round intermediate calculations. Round PVF values in intermediate calculations to four decimal places. Round the answer to whole percentage. %
Given the following Cash flows: C0 = - $6,750 C1 = $4,500 C2 = $18,000 Calculate...
Given the following Cash flows: C0 = - $6,750 C1 = $4,500 C2 = $18,000 Calculate the NPV of the above project for discount rates of 0%, 50%, and 100%. What is the IRR of the project?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT